This "Review" topic is provided to demonstrate a suggested change to the page.
The suggested change is implemented in the "PDR" tab to show the following changes.



Entrance and Exit Criteria
Background
This guidance provides the recommended life cycle review entrance and exit criteria for software projects and should be tailored for the project class.
This topic describes the recommended best practices for entrance and success criteria for the software life cycle and technical reviews required by NASA. The guidelines are regardless of whether the review is accomplished in a one-step or two-step process. The entrance and items reviewed criteria do not provide a complete list of all products and their required maturity levels. Additional programmatic products may also be required by the appropriate governing NPRs for the project/program.
Tailoring and customizing are expected for projects and programs. The entrance and success criteria and products required for each review will be tailored and customized appropriately for the particular program or project being reviewed and the classification of the software. The decisions made to tailor and customize life-cycle review criteria should be justified to both the Engineering and SMA TA.
The recommended criteria in the following tables are focused on demonstrating acceptable software technical maturity, adequacy of software technical planning and credibility of budget, software schedule, risks (as applicable), and software readiness to proceed to the next phase. Customized or tailored criteria developed by programs or projects for life-cycle reviews should also be focused on assessing these factors. The software entrance and exit criteria guidance is a collection of material from the following core documents: NPR 7150,2 083 requirements, NASA-STD-8739.8 278 requirements, and NPR 7123.1, Appendix G 041.
See also 7.08 - Maturity of Life Cycle Products at Milestone Reviews.
1.1 References
1.2 Additional Guidance
Additional guidance related to this requirement may be found in the following materials in this Handbook:
Related Links |
---|
1.3 Center Process Asset Libraries
SPAN - Software Processes Across NASA
SPAN contains links to Center managed Process Asset Libraries. Consult these Process Asset Libraries (PALs) for Center-specific guidance including processes, forms, checklists, training, and templates related to Software Development. See SPAN in the Software Engineering Community of NEN. Available to NASA only. https://nen.nasa.gov/web/software/wiki 197
See the following link(s) in SPAN for process assets from contributing Centers (NASA Only).
SPAN Links |
---|
System Definition Review (SDR)
The MDR (or SDR) examines the proposed requirements, the mission/system architecture, and the flow down to all functional elements of the system. (NPR 7120.5 082)
- MDR is equivalent to SDR for robotic projects.
Entrance Criteria |
---|
Software requirements |
Bi-directional traceability |
Completed Software Plans |
Completed software classification and safety criticality assessments are available |
Identification of software safety-critical components by having a preliminary software hazard analysis completed |
NASA NPR 7150.2 requirements mapping matrix is complete |
NASA-STD-8739.8 requirements mapping matrix is complete |
Software data dictionary |
Completed Software Safety Assessment |
Completed software assurance software requirements analysis |
Completed the IV&V software requirements analysis |
Completed peer review(s) of the software requirements |
Completed peer review(s) of the software plans |
Preliminary Human Rating Plan, if applicable |
Preliminary Maintenance Plan |
Software configuration management (CM) plan |
Completed IV&V Project Execution Plan |
Confirm RFAs and RIDs from MCR have been satisfactorily resolved |
Identify the software assurance, software safety, and IV&V personnel for the project and milestone review. |
The software assurance point of contact for the project has been identified. |
Items Reviewed |
---|
Requirements mapping table for the software assurance and software safety standard requirements |
Software requirements |
Interface requirements documents, including Software interfaces |
Hazard Analysis and software controls and mitigations (Functional Hazard Analysis / Hazard Reports / Hazard Analysis Tracking Index) |
Software and avionics architectures |
Software data dictionary |
Software assurance requirement analysis results |
Software classifications |
Software architecture |
Software Management Plan(s) |
Software process audit results |
Software verification and validation (V&V) planning |
Bidirectional traceability matrix. |
Technical resource utilization estimates and margins |
Software configuration management (CM) plan |
Software Assurance (SA) and Software Safety Plan(s), including SA Product Acceptance Criteria and Conditions. |
Software Development Plan |
Software peer review results |
Software Assurance schedule |
Software coding guidelines |
Software risks |
Software safety analysis results |
Cost estimate for the project’s Software Assurance support |
IV&V Project Execution Plan (if required) |
IV&V Project risk assessment (if required) |
System architecture, including avionics architecture |
Top technical, cost, schedule, and safety risks, risk mitigation plans, and associated resources |
Concept Documentation |
Exit / Success Criteria |
---|
The project’s software plans, schedules, resources, and requirements are sufficiently mature to begin Phase B. |
Quality software requirements have been established. |
Software Bi-directional traceability is complete. |
System Hazard Analyses address or include all known software hazards, |
The software NPR 7150.2 and NASA-STD-8739.8 requirements tailoring have been completed and approved by the required technical authorities and the project. |
Certifiable software development practices by the organizations developing the critical software components exist. |
Software metrics to track the software quality and maturity have been selected. |
Certifiable software development practices by the organizations developing the critical software components exist and are being followed. |
All known software risks are identified and technically assessed. |
IV&V concurs that the project’s software plans, schedules, resources, and requirements are sufficiently mature to begin Phase B. (If IV&V is required) |
Entrance Criteria | Items Reviewed | Exit / Success Criteria |
---|---|---|
Software requirements | Requirements mapping table for the software assurance and software safety standard requirements | The project’s software plans, schedules, resources, and requirements are sufficiently mature to begin Phase B. |
Bi-directional traceability | Software requirements | Quality software requirements have been established. |
Completed Software Plans | Interface requirements documents, including Software interfaces | Software Bi-directional traceability is complete. |
Completed software classification and safety criticality assessments are available | Hazard Analysis and software controls and mitigations (Functional Hazard Analysis / Hazard Reports / Hazard Analysis Tracking Index) | System Hazard Analyses address or include all known software hazards, |
Identification of software safety-critical components by having a preliminary software hazard analysis completed | Software and avionics architectures | The software NPR 7150.2 and NASA-STD-8739.8 requirements tailoring have been completed and approved by the required technical authorities and the project. |
NASA NPR 7150.2 requirements mapping matrix is complete | Software data dictionary | Certifiable software development practices by the organizations developing the critical software components exist. |
NASA-STD-8739.8 requirements mapping matrix is complete | Software assurance requirement analysis results | Software metrics to track the software quality and maturity have been selected. |
Software data dictionary | Software classifications | Certifiable software development practices by the organizations developing the critical software components exist and are being followed. |
Completed Software Safety Assessment | Software architecture | All known software risks are identified and technically assessed. |
Completed software assurance software requirements analysis | Software Management Plan(s) | IV&V concurs that the project’s software plans, schedules, resources, and requirements are sufficiently mature to begin Phase B. (If IV&V is required) |
Completed the IV&V software requirements analysis | Software process audit results |
|
Completed peer review(s) of the software requirements | Software verification and validation (V&V) planning | |
Completed peer review(s) of the software plans | Bidirectional traceability matrix. | |
Preliminary Human Rating Plan, if applicable | Technical resource utilization estimates and margins | |
Preliminary Maintenance Plan | Software configuration management (CM) plan |
|
Software configuration management (CM) plan | Software Assurance (SA) and Software Safety Plan(s), including SA Product Acceptance Criteria and Conditions. | |
Completed IV&V Project Execution Plan | Software Development Plan |
|
Confirm RFAs and RIDs from MCR have been satisfactorily resolved | Software peer review results | |
Identify the software assurance, software safety, and IV&V personnel for the project and milestone review. | Software Assurance schedule |
|
The software assurance point of contact for the project has been identified. | Software coding guidelines |
|
Software risks | ||
Software safety analysis results |
| |
Cost estimate for the project’s Software Assurance support | ||
IV&V Project Execution Plan (if required) | ||
IV&V Project risk assessment (if required) |
| |
System architecture, including avionics architecture | ||
Top technical, cost, schedule, and safety risks, risk mitigation plans, and associated resources | ||
Concept Documentation |