SWE-141 - Last used in rev NPR 7150.2D
| Rev | SWE Statement |
|---|---|
| A | |
| Difference between A and B | New |
| B | 3.6.2 For projects reaching KDP (Key Decision Point) A after the effective date of this directive’s revision, the program manager shall ensure that software IV&V (Independent Verification and Validation) is performed on the following categories of projects:
|
| Difference between B and C | Removed KDP acronym; removed the caveat "after the effective date of this directive's revision"; In item c, removed "specifically" and added "explicitly",; Spelled out the "CSMA" acronym by removing and replacing with "Chief of the Office of Safety and Mission Assurance". |
| C | 3.6.2 For projects reaching Key Decision Point A the program manager shall ensure that software IV&V is performed on the following categories of projects: |
| Difference between C and D | Item c. was updated to show change to MDAA for selection. |
| D | 3.6.2 For projects reaching Key Decision Point A, the program manager shall ensure that software IV&V is performed on the following categories of projects: a. Category 1 projects as defined in NPR 7120.5. |