SWE-066 - Last used in rev NPR 7150.2D
| Rev | SWE Statement |
|---|---|
| A | 3.4.2 The project shall perform software testing as defined in the Software Test Plan. |
| Difference between A and B | Removed reference to the Software Test Plan which is defined in SWE-104. |
| B | 4.5.3 The project manager shall perform software testing. |
| Difference between B and C | Instead of just performing testing, specifies testing shall be done against the requirements. |
| C | 4.5.3 The project manager shall test the software against its requirements. |
| Difference between C and D | No change |
| D | 4.5.3 The project manager shall test the software against its requirements. |