SWE-178 - Last used in rev NPR 7150.2D
| Rev | SWE Statement |
|---|---|
| A | |
| Difference between A and B | N/A |
| B | |
| Difference between B and C | NEW |
| C | 3.6.4 If software IV&V is performed on a project, the project manager shall ensure that IV&V is provided access to development artifacts, products, source code, and data required to perform the IV&V analysis efficiently and effectively. |
| Difference between C and D | No change. |
| D | 3.6.4 If software IV&V is performed on a project, the project manager shall ensure that IV&V is provided access to development artifacts, products, source code, and data required to perform the IV&V analysis efficiently and effectively. |


