SWE-086 - Last used in rev NPR 7150.2D
| Rev | SWE Statement |
|---|---|
| A | 4.2.1 The project shall identify, analyze, plan, track, control, communicate, and document software risks in accordance with NPR 8000.4, Agency Risk Management Procedural Requirements. |
| Difference between A and B | Added mitigation plans to scope of the requirement. |
| B | 5.2.2 The project manager shall identify, analyze, plan, track, control, communicate, and record software risks and mitigation plans in accordance with NPR 8000.4. |
| Difference between B and C | Removes the requirement to "identify"; Removed "in accordance with NPR 8000.4" |
| C | 5.2.1 The project manager shall record, analyze, plan, track, control, and communicate all of the software risks and mitigation plans. |
| Difference between C and D | No change |
| D | 5.2.1 The project manager shall record, analyze, plan, track, control, and communicate all of the software risks and mitigation plans. |