SWE-037 - Last used in rev NPR 7150.2D
| Rev | SWE Statement |
|---|---|
| A | 2.5.6 The project shall define the milestones at which the software supplier(s) progress will be reviewed and audited as a part of the acquisition activities. |
| Difference between A and B | No change |
| B | 3.12.6 The project manager shall define the milestones at which the software supplier(s) progress will be reviewed and audited as a part of the acquisition activities. |
| Difference between B and C | Added the requirement to document the milestones; Changed "supplier(s)" to "developer(s)"; Descoped the reqts by removing "as a part of the acquisition activities" |
| C | 3.1.7 The project manager shall define and document the milestones at which the software developer(s) progress will be reviewed and audited. |
| Difference between C and D | No change |
| D | 3.1.7 The project manager shall define and document the milestones at which the software developer(s) progress will be reviewed and audited. |