Last used in rev NPR 7150.2C

RevSWE Statement
A

4.3.3 The project shall, for each planned software peer review/inspections:

      a. Use a checklist to evaluate the work products.
      b. Use established readiness and completion criteria.
      c. Track actions identified in the reviews until they are resolved.
      d. Identify required participants.

Difference between A and B

Reworded with same intent

B

5.3.3 The project manager shall, for each planned software peer review or software inspection:

    1. Use a checklist or formal reading technique (e.g., perspective based reading) to evaluate the work products.
    2. Use established readiness and completion criteria.
    3. Track actions identified in the reviews until they are resolved.
    4. Identify required participants.
Difference between B and C

No change

C