4.3.3 The project shall, for each planned software peer review/inspections:

      a. Use a checklist to evaluate the work products.
      b. Use established readiness and completion criteria.
      c. Track actions identified in the reviews until they are resolved.
      d. Identify required participants.

Difference between A and BIncluded "formal reading technique" as mechanism for evaluating work products.
B

5.3.3 The project manager shall, for each planned software peer review or software inspection:

    1. Use a checklist or formal reading technique (e.g., perspective based reading) to evaluate the work products.
    2. Use established readiness and completion criteria.
    3. Track actions identified in the reviews until they are resolved.
    4. Identify required participants.
Difference between B and C

No change

C

Difference between C and D
D