UNDER CONSTRUCTION


Notes in this template provide guidance to authors on how the section if to be completed. Once the section is populated, the Note may be deleted. Notes are not intended to be left in the completed page. 

1. Introduction

Typically starts with a definition of the activity. Additional descriptive material is meant to help define the activity but not be so detailed that it pulls in all of the guidance from the SWEs in the activity. 

Planning of Software Assurance activities in a Software Development Project are done in a collaborative fashion along with the Software Development team. As a part of that collaboration, several Software Assurance tasks most be started. 


Activity graphical representation of Inputs, Outputs, Predecessor and Successor Activities as appropriate. Not meant to be exhaustive, but representative of a typical project. 

 1.1 Inputs

List of some of the inputs from other activities that are necessary for the activity to begin. 

Examples: 

  • Planning - Peer Reviews are planned activities. They appear in the plans and schedules for the project
  • Requirements - These are the things that are Peer Reviewed
  • Architecture Items - These are the things that are Peer Reviewed
  • Design items - These are the things that are Peer Reviewed
  • Test Plans and Procedures - These are the things that are Peer Reviewed

1.2 Predecessor Activities

List of some of the other activities that must be started (not necessarily completed) so that this activity may begin. 

Examples: 

Predecessor Activities are performed before Peer Reviews. These activities produce the work products that will be reviewed. 

  • Life Cycle Planning - plans, schedules, estimates, etc.
  • Software Architecture 
  • Software Design
  • Software Testing - plans and procedures

1.3 Outputs

List of some of the outputs or work products of the activity. These are typically used as inputs by the downstream activity. In some cases there is a supporting SWE associated with the work product. 

Examples: 


The activities that initiated the Peer Review, receive the findings from Peer Reviews, Those activities then use those findings to to fix defects and implement improvements uncovered in the reviews. 

Output Work ProductUsed by Downstream Activity
  • Peer Review Findings
  • Life Cycle Planning
  • Software Architecture 
  • Software Design
  • Software Testing
  • Configuration Management
  • Coding


1.4 Successor Activities

Links to Activities which might be started or supported by this activity. 


1.5 Activity Repetition

Describe what conditions determine if the activity needs to be repeated, such as re-planning after a change in requirements or schedule constraints. 

  • How much of the activity needs to be repeated
  • Frequency of repetition


1.6 Center Resources From SPAN

Add links to SPAN activity pages that are appropriate for this activity. Use links from the Activity section of the front page. SPAN

Several Centers Process Asset Libraries have materials related to this activity. Related Processes, templates, and other resources may be found in the following Activities in SPAN (available to NASA only). 


2. Defining the Activity

This tab contains the links to pages in the SWEHB or excerpts from the NASA-STD-8739.8B that are at the heart of the activity. 

2.1 SWEs

This section contains the links to SWE pages that form the heart of the activity. In the case of Software Assurance, copy in the task table from each of the tab 7.1 from appropriate SWEs. 

Link to the SWE goes here

  • Excerpt include for the SWE goes here (Remove Surrounding Panel)
SWERequirementSA Tasks

034

2.2 Topics and other Supporting Materials

This section is for SWEHB pages, other than SWEs, that directly support the activity. This section contains Topics, document content pages, PATs, and other pages. 

  • Link to the Topic or page goes here
    • Excerpt include for the Topic or page goes here (Remove Surrounding Panel)

2.3 Other Associated SWEs, Topics, etc.

Includes other SWEHB pages that are indirectly associated with the activity. May include SWEs, Topics, document definition pages, PATs, etc. They may have been mentioned in the guidance of another page. 

  • Include page for the PAT page goes here