3. Guidance3.1 Record Tailored RequirementsThe project is required to record tailored requirements in program/project documentation that controls the development, acquisition, and deployment of the affected software. Publication of the approved alternate requirements helps show accepted risks and assures that all affected software engineers are informed of the approved changes. This action assures the proper implementation of the alternate requirement throughout the various stages of the software life cycle. The inclusion of these changes in a configuration-managed system for the program/project will inform current and future software product developers and project managers of the correct set of requirements and procedures. The project should generate: - Develop a compliance matrix for the software requirements per the software classification.
- Develop a tailoring matrix of the software assurance and software safety requirements as needed and document the software assurance, and software safety approach in the software assurance plan and schedule.
- Add the compliance matrix and the software assurance and software safety tailoring matrix requirements in a software plan(s).
Project personnel records the appropriate information on any requirements changes resulting from the approval of a tailoring request in the project-specific software requirements documents. The Center's compliance matrix to NPR 7150.2 will also include approval of tailored requirements from the Office of the Chief Engineer (OCE). See also, 7.16 - Appendix C. Requirements Mapping and Compliance Matrix. SWE-139 - Shall Statements, 3.2 Updates to the Compliance MatrixSoftware requirements tailoring is the process used to seek relief from NPR requirements consistent with program or project objectives, acceptable risk, and constraints. To accommodate the wide variety of software systems and subsystems, the application of these requirements to specific software development efforts may be tailored where justified and approved. To effectively maintain control over the application of requirements in this directive and to ensure proposed tailoring from specific requirements are appropriately mitigated, NASA established Technical Authority (TA) governance. The Technical and Institutional Authority for each requirement in this NPR is documented in the “Authority” column of Appendix C (see topic 7.16 - Appendix C. Requirements Mapping and Compliance Matrix). The responsible program, project, or operations manager needs to formally accept the tailoring risk. General guidelines for SWE requirements, except for SWE-032 - CMMI Levels for Class A and B Software and SWE-141 - Software Independent Verification and Validation: - Each requirement marked ‘X’ for the project’s software classification(s) should be addressed in the Requirements Mapping Matrix.
- All requirements can be tailored per the guidance in this directive.
- Requirements Mapping Matrix with tailored requirements, deleted requirements, or requirements marked as N/A or not applicable need the approval of the Center Director’s designated Engineering Technical Authority and the Center Director’s designated SMA Technical Authority.
- If the project is a CHMO Health and Medical project, then CHMO designated Technical Authority approval is also required.
- If the project marks any of the requirements in Section 3.11 as a tailored requirement, a deleted requirement, or a requirement marked as N/A or not applicable then the project is required to get the NASA CIO approval on the Requirements Mapping Matrix, in addition to the technical authorities in item 3 and 4.
- The NASA CIO, or the designee, has institutional authority on all Class F software projects.
In the case of changes to SWE-032 - CMMI Levels for Class A and B Software and SWE-141 - Software Independent Verification and Validation, these steps are followed: - The Project Manager fills out the compliance matrix and indicates their tailoring to SWE-032 or SWE-141.
- The Project Manager sends the Compliance Matrix to the appropriate Center TA’s and requests approval of the changed requirements.
- The Project Manager communicates the proposed request to tailor SWE-032 and SWE-141 to the OCE and OSMA for an initial discussion.
- Appropriate Center TA’s approve the proposed changes to SWE-032 or SWE-141.
- The Project Manager and Center TA’s communicate the proposed changes and rationale on either SWE-032 or SWE-141 to the OCE and OSMA for discussion.
- After OCE and OSMA approval, the Project Manager stores all related records and updated Compliance Matrix into project records.
See also SWE-150 - Review Changes To Tailored Requirements, 3.3 Baselined TailoringWhen approval is granted, the program/project includes the results of the tailoring request and the rationale for the request, along with any approved alterations to the initial request, in the baselined program/project documentation. 3.4 Additional GuidanceAdditional guidance related to this requirement may be found in the following materials in this Handbook: 3.5 Center Process Asset Libraries
See the following link(s) in SPAN for process assets from contributing Centers (NASA Only). |