SWE-025 - Corrective Actions
Unknown macro: {div3}

1. Requirements

2.2.14 The project shall ensure that corrective actions are taken, recorded, and managed to closure when actual results and performance deviate from the software plans.

1.1 Notes">1.1 Notes

NPR 7150.2 does not include any notes for this requirement.

1.2 Applicability Across Classes

Classes D and E and Safety Critical are labeled with "SO". This means that this requirement applies to the safety-critical aspects of the software.

Class G is labeled with "P (Center)".  This means that an approved Center-defined process which meets a non-empty subset of the full requirement can be used to achieve this requirement.

Class

  A_SC 

A_NSC

  B_SC 

B_NSC

  C_SC 

C_NSC

  D_SC 

D_NSC

  E_SC 

E_NSC

     F      

     G      

     H      

Applicable?

   

   

   

   

   

   

    X

   

    X

   

   

    P(C)

   

Key:    A_SC = Class A Software, Safety Critical | A_NSC = Class A Software, Not Safety Critical | ... | - Applicable | - Not Applicable
X - Applicable with details, read above for more | P(C) - P(Center), follow center requirements or procedures

Unknown macro: {div3}

2. Rationale

The use of a good corrective action plan and related tools (usually referred to as a "PRACA" (Problem Reporting and Corrective Action System) makes sure that the software development and assurance teams understand, act upon, and close issues and discrepancies to prevent reoccurrence.  Proper documentation helps the teams to track the activity, know when it is complete, and when it is eligible to be closed.  It also provides measurement data input for project metric evaluations and the development of lessons learned information.

Unknown macro: {div3}

3. Guidance

The planning and requirements documentation developed during the early phases of the project (see [SWE-013], [SWE-102], and [SWE-109]) guides development of software work products. The project management team and the software development lead work together to construct a work plan that is logical and achievable in the allotted time. During early project phases key performance factors, schedules and milestones are composed. As scheduled work is performed it is important for the results to be reviewed to assure conformance with these plans and to assess if the expected performance has been achieved (see [SWE-024]). During these reviews (both formal and informal) project results are compared to plans. Tools such as excel-based checklists, planning and tracking tools such as Omniplan and Primavera, and/or formal configuration management systems/change control tools are used to identify, resolve, and track to closure discrepancies and other shortfalls to project performance.

It is important to understand that the activities of 'identification', 'recording', and 'tracking to closure' are techniques that the software development engineering team uses to address and satisfy NPR 7150.2 requirements related to many areas in the project, such as life cycle planning ([SWE-018] and [SWE-024]), verification and validation activities ([SWE-030] and [SWE-031]), requirements development and management ([SWE-054]), configuration management systems ([SWE-080]), and the preparation of documentation to measure and record these activities ([SWE-091], [SWE-102], [SWE-109], [SWE-113], and [SWE-117]). NPR 7150.2 uses these terms repetitively, but users of this Handbook are expected to use them and interpret them in the context of the SWE guidance being read.

Occasionally these reviews surface a significant discrepancy between the actual and expected results of an activity. Some discrepancies are a normal part of project development activity and are resolved through the normal course of scheduled activity. These discrepancies are typically tracked informally until the developers establish a product baseline, after which discrepancies/problems are formally tracked (usually in the PRACA system) which requires evaluation, disposition and assurance oversight of the problem.  The Software Development Plan or the Software Configuration Management Plan typically defines the level of the discrepancies that are required to be recorded and tracked in the formal tracking systems.   Typically a Center has an approved process for problem reporting and corrective action (PRACA) activities. This requirement does not mandate a particular approach or tool as long the key elements of a corrective action activity that are described in the following paragraph are employed.

During the course of the software development activity, once a discrepancy is found that meets the criteria for formal reporting, the software development team clearly states the issue, its area of applicability across the software development activity, and the spectrum of relevant stakeholders it involves. As this information is obtained the issue is documented in the approved process tool or data repository and an analysis is conducted of the discrepancy. The results of a properly completed analysis provide a clear understanding of the discrepancy and a proposed course of action to further investigate and resolve the discrepancy as necessary. [SWE-113] provides specific details for the information needed for documenting a problem report.

The proposed course of action may be reviewed by project management and other relevant stakeholders to assure resources are available for the activity (see [SWE-026]). It may be necessary to update planning documentation and development schedules to account for the corrective action activity (see [SWE-080]). Once a corrective action activity has been approved and initiated, its progress is reviewed on a regular basis for progress and its use of planned resources.  This information is used to assess whether the action itself is on course or deviating from the expected result.

An important element of the corrective action activity is the proper closeout of the action. After the activity has concluded, or when the discrepancy has been narrowed to within acceptable limits, the closeout is recorded and may include the following information:

  • Description of the issue/discrepancy
  • Proposed corrective action, with acceptable limits
  • Actual results/impacts from the effort
  • Listing of required changes to requirements, schedules, resources, if any, to accommodate the result
  • Signature(s)/concurrence by all relevant stakeholders

Once the documentation has been completed, it can be entered into a suitable repository or configuration management system.

Unknown macro: {div3}

4. Small Projects

This requirement applies to all projects regardless of size.

Unknown macro: {div3}

5. Resources

5.1 Tools

Tools relative to this SWE may be found in the table below. You may wish to reference the Tools Table in this handbook for an evolving list of these and other tools in use at NASA. Note that this table should not be considered all-inclusive, nor is it an endorsement of any particular tool. Check with your Center to see what tools are available to facilitate compliance with this requirement.

Tool nameTypeOwner/SourceLinkDescriptionUser

Primavera

COTS

Oracle

http://www.oracle.com/primavera ...

Primavera Project Manager is a critical path method (CPM) scheduling tool that is as part of a Project Portfolio Management software package.

OmniPlan

COTS

The Omni Group

http://www.omnigroup.com/products/omniplan ...

OmniPlan provides features like Gantt charts, schedules, summaries, milestones, and critical path highlighting

ARC

JIRA

COTS

Atlassian

http://www.atlassian.com/software/jira ...

JIRA provides issue tracking and project tracking for software development teams to improve code quality and the speed of development. It combines a clean, fast interface for capturing and organizing issues with customizable workflows, OpenSocial dashboards, and a pluggable integration framework. You can start with Atlassian software for $10. JIRA is used for issue tracking and project management by over 14,500 organizations.

GRC, JPL, GSFC, ARC

Bugzilla

Open Source

Bugzilla

http://www.bugzilla.org ...

Bugzilla is a robust, featureful and mature defect-tracking system, or bug-tracking system. Defect-tracking systems allow teams of developers to keep track of outstanding bugs, problems, issues, enhancement and other change requests in their products effectively. Version 5.0.4.

ARC, GSFC

Unknown macro: {div3}

6. Lessons Learned

 The NASA Lessons Learned database contains the following lessons learned related to corrective actions:

  1. Probable Scenario for Mars Polar Lander Mission Loss (1998), Lesson No. 0938: Description: Neither the MPL software requirements specification nor the software, subsystem or system test plans required verification of immunity to transient signals. MPL touchdown sensors generated known transient signals at leg deployment. Full leg deployment test was not repeated after wiring corrections. Tests should be re-run after test deficiencies are corrected or hardware or software is revised unless clear rationale exists for not doing so. Hardware operational characteristics, including transients and spurious signals must be reflected in software requirements and verified by test 529.  
  2. Problem Reporting and Corrective Action System, Lesson No. 0738. This Lesson Learned is based on Reliability Practice No. PD-ED-1255; from NASA Technical Memorandum 4322A, NASA Reliability Preferred Practices for Design and Test 520.