bannera

Book A.
Introduction

Book B.
7150 Requirements Guidance

Book C.
Topics

Tools,
References, & Terms

SPAN
(NASA Only)

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 45 Next »

The license could not be verified: License Certificate has expired! Administrators, please check your license details here.

SWE-106 - Software Assurance Plan
Unknown macro: {div3}

1.Requirement

5.1.5.1 The Software Assurance Plan(s) shall be developed and documented per NASA-STD-8739.8, NASA Software Assurance Standard.

1.2 Notes

NPR 7150.2 does not include any notes for this requirement.

1.3 Applicability Across Classes

Class

  A_SC 

A_NSC

  B_SC 

B_NSC

  C_SC 

C_NSC

  D_SC 

D_NSC

  E_SC 

E_NSC

     F      

     G      

     H      

Applicable?

   

   

   

   

   

   

   

   

   

   

   

   

   

Key:    A_SC = Class A Software, Safety-Critical | A_NSC = Class A Software, Not Safety-Critical | ... | - Applicable | - Not Applicable
X - Applicable with details, read above for more | P(C) - P(Center), follow center requirements or procedures

Unknown macro: {div3}

2. Rationale

Software assurance activities ensure that the project team implements software engineering products and processes according to the plans established by the project and comply with requirements in the NASA Software Assurance Standard. The NASA Software Assurance Standard 278captures the assurance requirements in a single place for more uniform application across projects where software is developed or acquired for NASA.

The Software Assurance Plan represents an agreement between the project, the software developers and the software assurance personnel. It describes the activities, roles, and responsibilities of software assurance on the project. As with any task, a plan helps ensure that the team performs all necessary and required tasks. Development of that plan provides the opportunity for stakeholders to give input and assist with the documentation and tailoring of the planned activities for the project.

Specific to software assurance, the NASA Software Assurance Standard 278provides requirements that the team can use as the basis for development of a project's software assurance plan. Using this previously thought-out, defined set of requirements gives plan development teams a common starting point for their activities and ensures that all software assurance plans include and address the same key tasks and assurance activities.

Unknown macro: {div3}

3. Guidance

?

Per NPR 7150.2, "The Software Assurance Plan details the procedures, reviews, and audits required to accomplish software assurance. The project office should coordinate with the Office of Safety and Mission Assurance for help in scoping and adapting the effort appropriately, and to designate the individual responsible for software assurance on the project."   

For projects that involve contracted work, both the acquirer and the provider (subcontractor), need Software Assurance Plans and those plans must work together to accomplish the required level of software assurance. The preliminary acquirer plan is developed at the same time the Request for Proposal (RFP) or Memorandum of Agreement/Understanding (MOA/U) is created. Both acquirer and provider plans are to be completed by the time the contract is awarded, though an update of the provider plan is expected at the SwRR.

As with many project plans, the Software Assurance Plan (SAP) may be a separate document or may be combined with another project plan such as the Software Development Plan (SDP).  However, the independent software assurance organization of the Acquirer SMA Office needs to have sign-off authority on the content no matter what document the SAP contents may be incorporated into.  The SAP is a joint agreement between Acquirer SMA and the project/facility for software assurance activities.

While the NASA Software Assurance Standard 278contains requirements for software assurance in general, it also contains minimum content requirements for the SAP.  The following requirements, identified by the NASA Software Assurance Standard paragraph numbers, apply specifically to the development and documentation of a SAP. These requirements, shown here without their associated project life cycle phase, provide a high-level content overview of both the acquirer and provider SAPs. When carrying out these requirements, consult the NASA Software Assurance Standard 278to determine the specific life cycle phase in which they are to be completed.

Acquirer SAP:

  • 5.1.2.8 - Prepare a preliminary acquirer program/project software assurance plan documenting the planned level of software assurance effort and activities required and the necessary resources using the template provided in Appendix B [of the NASA Software Assurance Standard 278].
  • 5.3.1.1 - Verify that the provider's software assurance plan meets contractual requirements.
  • 5.3.1.2 - Verify that the acquirer's software assurance plan and the provider's software assurance plan are consistent, compatible, and are base-lined.

Provider SAP:

  • 6.3.1 - Each software provider shall establish and maintain a software assurance plan that addresses all software development and maintenance activities.
    NOTE: For smaller projects, this plan may be incorporated in another project-planning document or may be a separate document. Larger projects may have a separate plan or more than one software assurance plan.
  • 6.3.2 - The software assurance plan shall:
  • 6.3.2.1 - Conform to IEEE 730-2002, IEEE Standard for Software Quality Assurance Plans 218.
  • 6.3.2.2 - In addition, address how the provider will implement the requirements of Sections 6.0 and 7.0 of this Standard [NASA Software Assurance Standard 278].

The NASA Software Safety Standard, NASA-STD-8719.13B, 271also includes two requirements that address content to consider for the SAP:

  • 6.2.2.1 - The ?[safety] analysis methodology [for software design] shall be recorded in an appropriate document (e.g., software safety plan or software assurance plan).
  • 6.3.2.1 - The ?[safety] analysis methodology [for software implementation, e.g., code] shall be recorded in an appropriate document (e.g., software safety plan or software assurance plan).

Before writing a SAP, it is recommended that the team review the following material as preparation:

  • Software assurance lessons learned from similar projects
  • Existing software assurance processes, standards, procedures, etc.
  • Software assurance deliverables (records, reports, etc.) for similar projects

Using an existing template will ensure consistency of plans across projects as well as ensure all key information is included in the SAP. If a project or Center SAP template or "best-in-class" example does not exist, the NASA Software Assurance Standard, NASA-STD-8739.8, 278contains a basic outline in Appendix B. Templates are included in the Resources section of this guidance, including one from Goddard Space Flight Center (GSFC) based on the IEEE 730-2002 standard noted in the NASA Software Assurance Standard 278requirements which includes suggested content for each section of the SAP.

Other content elements to consider include:

  • Software assurance organization and management structure and responsibilities
  • Software assurance planning activities
  • Software classification and safety criticality
  • Software assurance implementation activities covering all 5 assurance disciplines:
    • Software Quality (includes software quality assurance, software quality engineering, and software quality control)
    • Software Safety
    • Software Reliability
    • Software Verification and Validation
    • Independent Verification and Validation
  • Standards and processes to be used, including those used for:
    • Software assurance implementation activities such as reviews, audits, etc.
    • Problem reporting and tracking
    • Risk management
    • Software assurance metrics (e.g., planned vs. actual reviews, audits, assessments; open vs. closed issues; number of identified risks; etc.)
    • Record creation, review, and maintenance
  • Training for software assurance personnel
  • Resources, including tools, personnel, and facilities
  • Identification of products and processes to be reviewed or audited
  • Identification of deliverables (records) to be created and maintained
  • Schedule

Ensure that the SAP is reviewed prior to implementation and at appropriate life cycle reviews by personnel with sufficient software assurance knowledge to identify omissions, inadequacies, and other issues. Include stakeholders affected by the plan in the reviews for awareness of planned activities and so that their suggestions can be addressed within the bounds of the project's required level of software assurance. Any identified issues need to be corrected prior to plan implementation or prior to carrying out affected software assurance activities in the next life cycle phase.

The following diagram excerpted from the Glenn Research Center SQA Process for Software Assurance, SEGP-SQA-PRC-1 382, shows a basic flow of activities for developing and documenting a SAP:

Any changes to the baselined SAP (typically baselined at

<ac:macro ac:name="unmigrated-wiki-markup">
<ac:plain-text-body><![CDATA[

PDR

]]></ac:plain-text-body>
</ac:macro>

) need to be made via the appropriate formal change request process (internal to the project for the acquirer SAP or via NASA's formal change request process for the provider SAP) and be accompanied by a risk analysis to ensure the project's level of software assurance is not compromised. 

The acquirer software assurance personnel are responsible for ensuring the provider software assurance personnel are meeting the contents of the provider SAP. The acquirer SAP describes how this will be done (based on software size, software class, safety-criticality, and other factors that may be specific to a project). 

Guidance related to software assurance and to be considered for inclusion in the SAP may be found in the following topics and requirements in this handbook:

[SWE-013]

Software Plans

[SWE-020]

Software Classification

?[SWE-022]

Software Assurance

[SWE-132]

Independent Software Classification Assessment

[SWE-133]

Software Safety Determination


Unknown macro: {div3}

4. Small Projects

According to the NASA Software Assurance Standard 278, smaller projects have the choice of incorporating their SAP in another project planning document or using a separate document.

Unknown macro: {div3}

5. Resources

5.1 Tools

Tools to aid in compliance with this SWE, if any, may be found in the Tools Library in the NASA Engineering Network (NEN).

NASA users find this in the Tools Library in the Software Processes Across NASA (SPAN) site of the Software Engineering Community in NEN.

The list is informational only and does not represent an “approved tool list”, nor does it represent an endorsement of any particular tool. The purpose is to provide examples of tools being used across the Agency and to help projects and centers decide what tools to consider.

Unknown macro: {div3}

6. Lessons Learned

There must be a software assurance plan.  "Most Project Managers feel they have too many plans, and the suggestion of another one for Software Quality Assurance might be the proverbial straw that breaks the camel's back! But the success of any undertaking is to know what one is trying to achieve and how one expects to accomplish it, hence, the necessity of a plan for SQA. The plan will specify the goals, what is to be performed, standards against which the development work is to be measured, all relevant procedures, and the organizational structure of the Quality Assurance within the project. At NASA a software assurance plan is required." (Lesson 4 of 12, SoftwareTech News 433).

The NASA Lesson Learned database contains the following lessons learned related to software assurance planning:

  • Quality Assurance Access to Critical Areas, Management (Quality Assurance Access). Lesson Number 0332:: "If program or engineering management exercises the authority to deny

    <ac:macro ac:name="unmigrated-wiki-markup">
    <ac:plain-text-body><![CDATA[

    QA

    ]]></ac:plain-text-body>
    </ac:macro>

    access to critical areas, QA over-site will be severely [compromised]."  [Note that while this lesson does not specifically call out software, the lesson remains relevant regarding assurance personnel access to information and areas required to perform software assurance activities.] 503
  • Quality Assurance Expertise in Special Technical Areas (e.g., optics) (Quality Assurance Expertise). Lesson Number 0331: "If quality assurance personnel responsible for oversight of the quality of highly technical state-of-the-art development do not have a degree of expertise in that technical area, the likelihood of discovering QA problems decreases significantly." [Note that while this lesson does not specifically call out software, the lesson remains relevant regarding assurance personnel access to information and areas required to perform software assurance activities.] 502
  • International Space Station (ISS) Program/Computer Hardware-Software/Software (Schedules). Lesson Number 1062: "The

    <ac:macro ac:name="unmigrated-wiki-markup">
    <ac:plain-text-body><![CDATA[

    ISS

    ]]></ac:plain-text-body>
    </ac:macro>

    software development schedule is almost impossibly tight. If something else does not cause a further delay in ISS deployment, software development may very well do so. The decision this year to add integrated testing of some modules ... is a very positive step for safety. However, there is no room in the schedule for required changes that may be discovered during this testing." 536
  • No labels