4.5 Principles Related to Tailoring the Standard Requirements
following steps. Tailoring at the Center level is decided by the SMA TA and the NPR 7150.2 Requirements Mapping Matrix applicability. Tailor the software assurance, software safety, and IV&V requirements using the following levels:
a. The first level of tailoring is the Software Classification Decision, see NPR 7150.2.
b. The second level of tailoring is the project’s Software Requirements Mapping Matrix, see NPR 7150.2.
c. The third level of tailoring is the tailoring by the Software Assurance TA of the Software Assurance and Software Safety Standard requirements that correspond to the project’s Software Requirements Mapping Matrix requirements.
4.5.6 If a system or subsystem development evolves to meet a higher or lower software classification defined in NPR 7150.2, the software assurance, software safety, and IV&V organizations shall update their plan(s) to fulfill the applicable requirements per the Requirements Mapping Matrix and any approved changes and initiate adjustments to applicable contracts to meet the modified requirements.