1. The Requirement
1
2. Rationale
2
3. Guidance
3
4. Small Projects
4
5. Resources
5
6. Lessons Learned
6
7. Software Assurance
Div
id
tabs-1
1. Requirements
Excerpt
5.4.6 The project manager shall collect, track, and report software requirements volatility metrics.
1.1 Notes
Software requirements volatility metrics are the total number of requirements compared to requirement changes over time. It may include additions, changes, and reduction of requirements.
1.2 History
Expand
title
Click here to view the history of this requirement: SWE-200 History
Include Page
SITE:SWE-200 History
SITE:SWE-200 History
1.3 Applicability Across Classes
Applicable c
a
1
b
1
csc
1
c
0
d
0
dsc
1
e
0
f
0
g
0
h
0
Div
id
tabs-2
2. Rationale
Requirements volatility is one of the leading causes of the software development effort not completing on schedule and budget. Software requirements volatility is one key factor in assessing the status of a software project. The later in the project requirements changes occur, the more impact those changes can have on project completion on time and budget.
Div
id
tabs-3
3. Guidance
This requirement applies to all NASA centers for Class A and B software. Class C software development efforts may also consider collecting these metrics, especially if the development schedule is very tight.
Requirements changes can occur throughout the entire lifecycle. Requirements changes for clarification or to add something that was overlooked are usually caught fairly early on in the lifecycle. In general, by PDR most requirements have been identified and refined. The cost of these changes, before PDR, is anticipated in the overall cost of the project.
It is important to keep track of requirements changes, especially later in the development lifecycle, so that an assessment can be made of the impact of these changes on the overall project cost and schedule. This assessment allows the project manager to make better-informed decisions on the implementation of the changes. Tracking requirements volatility over time can help identify potential process improvements that need to be made to enhance efficiency and productivity in the future.
Requirements volatility metrics are reported to the project manager and others regularly. They are also reported to the Software Engineering Process Group (SEPG) to help with future project cost estimation.
Some metrics to consider are:
Monitor and control changes in the software scope.
Number of requirements
Number of requirements changes
Number of TBR/TBDs over time
Assess the extent and cost of product rework.
Rework trend over time
Cost of the rework
Div
id
tabs-4
4. Small Projects
No additional guidance is available for small projects.
Div
id
tabs-5
5. Resources
5.1 References
refstable
Show If
group
confluence-users
Panel
titleColor
red
title
Visible to editors only
Enter the necessary modifications to be made in the table below:
SWEREFs to be added
SWEREFS to be deleted
SWEREFs NOT called out in text but listed as germane: none
SWEREFs called out in text: none
5.2 Tools
Include Page
Tools Table Statement
Tools Table Statement
Div
id
tabs-6
6. Lessons Learned
6.1 NASA Lessons Learned
No Lessons Learned have currently been identified for this requirement.
6.2 Other Lessons Learned
No other Lessons Learned have currently been identified for this requirement.
Confirm that the project collects, tracks, and reports on the software volatility metrics.
Analyze software volatility measures to evaluate requirements stability as an early indicator of project problems.
7.2 Software Assurance Products.
SA analysis of software volatility measures over time.
Note
title
Objective Evidence
Software measurement or metric data showing software volatility
Trends and analysis results on the metric set being provided
Status presentation showing metrics and treading data
Expand
title
Definition of objective evidence
Include Page
SITE:Definition of Objective Evidence
SITE:Definition of Objective Evidence
7.3 Metrics
Software Requirements Volatility (# of requirements added, deleted, modified, # of TBDs over time)
Note: Metrics in bold type are required for all projects
7.4 Guidance
Requirements volatility is the change in requirements (added, deleted, and modified) over a given time interval. The success of software projects is dependent on the quality of requirements, especially given that requirements are the basis for planning project schedules as well as design and test specifications.
Examples:
Software requirements volatility is expected during the early stages of a project (conceptualize / requirements phase). It becomes a concern when it occurs after the software requirements phase (after CDR) is complete because it is likely to result in the re-work of the software components.
Even though there are good requirements, in the beginning, the software requirements may be changed during the project development. Software requirement changes during the software development process are also known as Requirements Volatility.
Requirements volatility has a great impact on the cost, the schedule, and the quality of the final product. Due to requirements volatility, many projects fail and some are completed partially. Requirements volatility cannot be overcome fully but we can minimize it with some requirement measures or metrics. Requirement metrics are useful in identifying the risks of a project by locating errors in the requirements document.
Requirements evolution is due to factors.
External Factors:
Government regulations
project direction and changes
project funding
Internal factors
Hardware and interface constraints and unknowns
Lack of experience of the system requirements and software requirements development team
Feedback from milestone reviews and peer reviews
Complexity
Customer, operational, software, and hardware changes
Hazard identifications
Lack of process maturity in requirements generation and requirements management
Requirement or hardware reuse
Environmental changes or mission profile changes
Requirements instability (the extent of fluctuation in user requirements)
Requirements diversity (the extent to which stakeholders disagree among themselves deciding on requirements).
Requirements analyzability (the extent to which the process of producing requirement -specification can be reduced to objective procedure).
Poor communication between users and the development team.
Requirements volatility contains schedule, cost, and performance risk factors. Developing and maintaining a trending of software requirements volatility measurements is critical to determine the risks associated with the project.
Requirement volatility is not the only reason contributing to the success of any project, by can be a key indicator in the project risk and success.
Several challenges lead to Requirement Volatility.
The change request form was not always complete. A change request form may have little information about the reason for the proposed change.
No formal impact analysis and incomplete change effort estimation.
Traceability between requirements and other software artifacts is not established. See SWE-052
The impact of requirement volatility on the software project has been seen as:
Projects Schedule: If the schedule of one activity delays, obviously all subsequent activities schedule will be disturbed.
Project Performance: Project performance decreases due to the changes in requirements. Requirement Volatility has a high impact on the coding and maintenance phases.
Project Cost: Project cost increases due to a change in requirements.
S/W Maintenance
S/W Quality: Quality of software decreases due to continuous changes in requirements.
Though requirements volatility has an impact on the project schedule, project performance, project cost, software maintenance, and software quality, it may have some positive effects as well as it may help us to have a better understanding of user requirements.