01. The Requirement
12. Rationale
23. Guidance
34. Small Projects
45. Resources
56. Lessons Learned
67. Software Assurance
Div
idtabs-1

1. Requirements

Excerpt

4.6.5 The project manager shall maintain the software using standards and processes per the applicable software classification throughout the maintenance phase. 

1.1 Notes

NPR 7150.2, NASA Software Engineering Requirements, does not include any notes for this requirement.

1.2 History

Expand
titleClick here to view the history of this requirement:
 
SWE-195 History

Include Page
SITE:SWE-195 History
SITE:SWE-195 History

1.3 Applicability Across Classes

 

Applicable c
a1
b1
csc1
c1
d1
dsc1
e0
f1
g0
h0

Div
idtabs-2

2. Rationale

Standards and processes are documented in the SDP-SMP - Software Development - Management Plan or in a separate Maint - Software Maintenance Plan.  Each software classification has a defined set of requirements and all software at that classification must meet those requirements for its lifetime or until its classification changes, therefore, the software is maintained according to processes and standards defined for its software classification.

Div
idtabs-3

3. Guidance

Once the software classification is determined as defined in SWE-020, standards, and processes for the applicable software classification are defined in the Software Development/Management Plan (see Topic 7.18) to be used throughout the software lifecycle. The software is maintained using the defined and documented processes and standards throughout the maintenance phase.

Software Lifecycle

The Software development life cycle model includes the following phases.

1) Requirement gathering and analysis:  Business requirements are gathered in this phase. After requirement gathering, these requirements are analyzed for their validity and the possibility of incorporating the requirements in the system to be developed is also studied. A Requirement Specification document is created which serves the purpose of guideline for the next phase of the model.

2)  Design:  In this phase, the system and software design are prepared from the requirement specifications which were studied in the first phase. System Design helps in specifying hardware and system/software requirements and also helps in defining overall system architecture. The software design specifications serve as input for the next phase of the model.

3)  Implementation / Coding:  On receiving system/software design documents, the work is divided into modules/units and actual coding is started. Since, in this phase, the code is produced so it is the main focus for the developer. This is the longest phase of the software development life cycle.

4)  Testing:  After the code is developed it is tested against the requirements to make sure that the product is solving the needs addressed and gathered during the requirements phase. During this phase, all types of functional testing like unit testing, integration testing,  system testing,  acceptance testing are done as well as non-functional testing are also done.

5)  Deployment/Release: After successful testing, the product is delivered/deployed to the customer for their use.

6) Maintenance: Once when the customers start using the developed system then the actual problems come up and need to be solved from time to time. This process where the care is taken for the developed product is known as maintenance.

The Maintenance Phase is the last phase of the lifecycle and occurs once the system is released to the customer and operational. It includes implementation of changes that software might undergo over some time, or implementation of new requirements after the software is deployed at the customer location. The maintenance phase also includes handling the residual errors that may exist in the software even after the testing phase. This phase also monitors system performance, rectifies bugs, and requested for changes to be made. Maintenance is what happens during the rest of the software’s life: changes, correction, additions, moves to a different computing platform, and more.

Div
idtabs-4

4. Small Projects

No additional guidance is available for small projects.

Div
idtabs-5

5. Resources

5.1 References

refstable
Show If
groupconfluence-users
Panel
titleColorred
titleVisible to editors only

Enter the necessary modifications to be made in the table below:

SWEREFs to be addedSWEREFS to be deleted


SWEREFs NOT called out in text but listed as germane: none

SWEREFs called out in text: none


5.2 Tools

Include Page
Tools Table Statement
Tools Table Statement

Div
idtabs-6

6. Lessons Learned

6.1 NASA Lessons Learned

No Lessons Learned have currently been identified for this requirement.

6.2 Other Lessons Learned

No other Lessons Learned have currently been identified for this requirement.

Div
idtabs-7

7. Software Assurance

Excerpt Include
SWE-195 - Software Maintenance Phase
SWE-195 - Software Maintenance Phase

7.1 Tasking for Software Assurance

  1. Perform audits on the standards and processes used throughout maintenance based on the software classification.

7.2 Software Assurance Products

  • Standards and Processes Audit Report (Results of audits on processes and standards used during maintenance, including any findings, issues.)


    Note
    titleObjective Evidence
    • Software assurance process audit results
    Expand
    titleDefinition of objective evidence

    Include Page
    SITE:Definition of Objective Evidence
    SITE:Definition of Objective Evidence

7.3 Metrics

  • # of Non-Conformances identified in the software after delivery
  • # of process Non-Conformances (e.g., activities not performed) identified by SA vs. # accepted by the project
  • Trends of # Open vs. # Closed over time
  • # of Non-Conformances per audit (including findings from process and compliance audits, process maturity)
  • Trends of # of Non-Conformances from audits over time (Include counts from process and standards audits and work product audits.)
  • # of Open vs. Closed Audit Non-Conformances over time
  • # of Compliance Audits planned vs. # of Compliance Audits performed
  • # of software process Non-Conformances by life-cycle phase over time

7.4 Guidance

Software assurance will perform audits of the maintenance processes and procedures in use during this phase. Some of the processes and procedures to audit include the configuration management processes, change management processes, the process to transition changed software into the operational environment, and the testing procedures, particularly those associated with testing safety-critical functions and regression testing. 

Findings from the audit all need to be recorded and tracked to closure.

Every task that involves performing an audit should also clarify that all audit findings are promptly shared with the project will be addressed in the handbook guidance.

...