bannerc

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migration of unmigrated content due to installation of a new plugin
Tabsetup
01. The Requirement
12. Rationale
23. Guidance
34. Small Projects
45. Resources
56. Lessons Learned
67. Software Assurance
Div
idtabs-1

1. Requirements

Excerpt

3.6.5 If software IV&V is performed on a project, the project manager shall provide responses to IV&V submitted issues and risks, and track these issues and risks to closure. 

1.1 Notes

NPR 7150.2, NASA Software Engineering Requirements, does not include any notes for this requirement.

1.2 History

Expand
titleClick here to view the history of this requirement: SWE-179 History

Include Page
SITE:SWE-179 History
SITE:SWE-179 History

1.3 Applicability Across Classes

 

Applicable c
a1
b1
csc1
c0
d0
dsc1
e0
f0
g0
h0

Div
idtabs-2

2. Rationale

 If the project manager does not address the issues and risks found by IV&V and track them to closure, these unaddressed risks and issues could cause the project to fail to meet its objectives (e.g. schedule, planned quality, functionality, etc.) Since IV&V personnel have generally worked across many projects, they are often likely to recognize risks and issues to the project that the project manager may not recognize.

Div
idtabs-3

3. Guidance

If software-independent validation and verification (IV&V) are performed on a project, the project manager provides responses to IV&V submitted issues and risks and tracks these issues and risks to closure. 

IV&V is a part of Software Assurance playing a role in the NASA software risk mitigation strategy.  IV&V is an objective examination of safety and mission-critical software processes and products.  The key parameters for independence are technical independence, managerial independence, and financial independence.  The goal of IV&V is to determine if the right system has been built and that it has been built correctly.  From that perspective IV&V strives to answer the questions:  will the system’s software do what it is supposed to do, will the system’s software not do what it is not supposed to do and will the system’s software respond as expected under adverse conditions.

IV&V leads to higher quality products, reduced risk, greater insight, reduced cost, and knowledge transfer.  IV&V also facilitates the transfer of system and software engineering best practices. IV&V status reports provide another status indicator and performance report to decision-makers (program managers). The scope of IV&V services is determined by the IV&V provider, documented in the IV&V Project Execution Plan (IPEP)

Swerefn
refnum028
, and approved by the NASA IV&V Program. The IPEP is developed by the IV&V provider and serves as the operational document that will be shared with the project receiving IV&V support.

Once a risk or issue is submitted by IV&V, use the following considerations:

Considerations for evaluating the change and suggested solution

  • Project impact analysis.
    • Include the appropriate set of stakeholders, such as procurement, quality assurance, risk management, relevant experts, management (e.g., change requested by high visibility customer may result in a business decision to implement a change as opposed to volumes of end-users not seeing the problem), etc.
    • Evaluate the impact on schedule and cost, including making and testing the change and regression testing the software.
    • Evaluate the impact on other groups and resources, as applicable.
    • Evaluate the impact on functions and features, interfaces, system resource requirements.
    • Evaluate the impact on other baseline products, such as design, tests, documentation (traceability matrices are helpful here).
    • Evaluate the risk of making the change vs. not making it.
    • Evaluate the size, complexity, the criticality of the change.
    • Evaluate whether a change request is within the scope of the project.
    • Evaluate whether a change request is needed to meet project requirements.
    • Evaluate the impact on performance, reliability, quality, etc.
    • Evaluate alternatives to making the change.
  • Software safety impact analysis (NASA-STD-8739.8
    Swerefn
    refnum278
    , NASA Software Assurance, and Software Safety Standard )
    • Include software quality assurance, safety personnel in this review.
    • Look for the potential creation of new hazard contributions and impacts.
    • Look for potential modification of existing hazard controls or mitigations.
    • Look for a detrimental effect on safety-critical software or hardware.
    • Determine the effect on software safety.
    • Determine the effect on system safety.
  • Capture evaluation/analysis results and related decisions, including action items.

Considerations for tracking the change

  • Use a change control system that is compatible with the project environment and capable of tracking change until completed.
  • Trace safety-critical problems back to the related system-level hazard.
  • Include in the tracking records the actual change request/problem reports, impact analysis, notes from evaluation/approval boards and meetings, etc.
  • Track the software products and versions changed as part of implementing the change (requirements, code, specifications, etc.)
  • Close change requests only after verification and approval of the implemented change and all associated documentation revisions.

Once the evaluation of issues and risks have been evaluated, responses are submitted to IV&V. The risks and issues are tracked until closure. The project will continue to work with IV&V collaboratively to achieve consensus on issues and risks as both are dispositioned to closure.

Additional guidance related to IV&V may be found in the following related requirement in this Handbook:

Div
idtabs-4

4. Small Projects

No additional guidance is available for small projects.

Div
idtabs-5

5. Resources

5.1 References

refstable
Show If
groupconfluence-users
Panel
titleColorred
titleVisible to editors only

Enter the necessary modifications to be made in the table below:

SWEREFs to be addedSWEREFS to be deleted
SWEFER 271 - added
SWEREF IV&V Project Execution Plan (IPEP) - added SWEREF-028
added SWEREF-278 NASA-STD-8739.8

SWEREFs called out in the text: 028, 278

SWEREFs NOT called out in text but listed as germane: 271



5.2 Tools

Include Page
Tools Table Statement
Tools Table Statement
 

Div
idtabs-6

6. Lessons Learned

6.1 NASA Lessons Learned

No Lessons Learned have currently been identified for this requirement.

6.2 Other Lessons Learned

No other Lessons Learned have currently been identified for this requirement.

Div
idtabs-7

7. Software Assurance

Excerpt Include
SWE-179 - IV&V Submitted Issues and Risks
SWE-179 - IV&V Submitted Issues and Risks

7.1 Tasking for Software Assurance

  1. Confirm that the project manager provides responses to IV&V submitted issues, findings, and risks and that the project manager tracks IV&V issues, findings, and risks to closure.

7.2 Software Assurance Products

  • Records of IV&V issues and risks with status (e.g., accepted, in work, closed)


    Note
    titleObjective Evidence
    • Evidence that the confirmation of IV&V involvement is occurring, if applicable.
    Expand
    titleDefinition of objective evidence

    Include Page
    SITE:Definition of Objective Evidence
    SITE:Definition of Objective Evidence

7.3 Metrics

  • # of software work product Non-Conformances identified by life-cycle phase over time
  • # of Risks identified in each life-cycle phase (Open, Closed)
  • # of Risks by Severity (e.g., red, yellow, green) over time
  • # of Risks with mitigation plans vs. total # of Risks
  • # of Risks trending up over time
  • # of Risks trending down over time
  • # of IV&V Non-Conformances/issues/risks (# Open, Closed, accepted by the project, severity, category of Non-Conformance (e.g., requirements, design, code, testing, security, etc.))
  • The trend of open/closed Non-Conformances

7.4 Guidance

  1. Confirm if IV&V is required on the project, see section 4.4 of NASA-STD-8739.8
    Swerefn
    refnum278
    for the IV&V requirements.- See SWE-141 - Software Independent Verification and Validation
  2. Develop, if IV&V is required on the project, IV&V findings, issues, concerns, and risks. -
    • Assure that the IV&V findings, issues, concerns, and risks are tracked and addressed by the project and engineering. Track findings to closure. The IV&V personnel deliver their findings, concerns, and risks to the project periodically, and generally provide a summary status at milestone reviews. SA should have access to the IV&V findings and be able to review them to assure that they are being closed out in a timely fashion. If the findings and issues are not being addressed by the project, that should be elevated up through the assurance chain of command.
    • Identify software risks from the IV&V issues, concerns, and risks if needed. SA documents any software risks they identify from their review of the IV&V issues, concerns, and risks
    • Assess why the IV&V issues, concerns, and risks were not found during the SA assessment processes. SA reviews the IV&V issues, concerns, and findings and compares them to the SA findings to identify any findings that were not also identified by the SA team. Those IV&V findings not also identified by SA should be assessed to determine why they were not discovered. Assess SA processes as appropriate to enable the discovery of more of these missed findings.