01. The Requirement
12. Rationale
23. Guidance
34. Small Projects
45. Resources
56. Lessons Learned
67. Software Assurance
Div
idtabs-1

1. Requirements

Excerpt

3.2.1 To better estimate the cost of development, the project manager shall establish, document, and maintain:

    1. Two cost estimate models and associated cost parameters for all Class A and B software projects that have an estimated project cost of $2 million or more.
    2. One software cost estimate model and associated cost parameter(s) for all Class A and Class B software projects that have an estimated project cost of less than $2 million.
    3. One software cost estimate model and associated cost parameter(s) for all C and D software projects.
    4. One software cost estimate model and associated cost parameter(s) for all Class F software projects.

1.1 Notes

NPR 7150.2, NASA Software Engineering Requirements, does not include any notes for this requirement.

1.2 History

Expand
titleClick here to view the history of this requirement: SWE-015 History

Include Page
SITE:SWE-015 History
SITE:SWE-015 History

1.3 Applicability Across Classes

Applicable c
a1
b1
csc1
c1
d1
dsc1
e0
f0
g0
h0

Div
idtabs-2

2. Rationale

Because estimates are now prepared much earlier in the acquisition lifecycle, well before concrete technical information is available, they are subject to greater uncertainty than they have been in the past. Establishing two independent cost estimates for all software class A and B projects that have an estimated project cost of 2 million dollars reduces the uncertainty of the cost estimation and better validates the software cost estimation on large software projects. Credible software cost estimates are a key activity performed as part of a project and software lifecycle management (NPR 7150.2, NASA Software Engineering Requirements, Section 3.2) with regular updates made throughout the entire lifecycle. Unreliable cost estimates result in severe problems in planning and budgeting, which then result in staffing and budgeting decisions that could impair the effective use of resources.

Div
idtabs-3

3. Guidance

The key parts of the requirement that need to be addressed as a collaborative effort among software project managers and Center project and cost offices are:

  • Establish a software cost estimation process.  Preferably a project will use an industry-standard process or tool like Constructive Cost Model (COCOMO™) or Software Evaluation and Estimation of Resources - Software Estimating Model (SEER® SEM) tailored for the organization performance and parameters.
  • Document the process, parameters, and results of the software estimations.  Maintain records of the software estimates and data associated with uncertainly and assumptions for the given estimate.
  • Document and maintain all associated software cost parameters.  The ability to reproduce the software estimate and understand the risk associated with the estimate is generally contained in the software cost model parameters.
  • The cost estimate covers the entire lifecycle given the starting point of the estimate. 
  • Cost estimates are developed and maintained over the software lifecycle including any time the schedule or resource allocations change or requirements change.
  • Different software cost estimates are developed for the different classes of software on a project and different organizations developing software on a project.  Software cost parameters are maintained for each software cost estimate.

As software’s importance in missions has grown, the focus on its overall performance both technically and programmatically has also increased. As a result, the software has been blamed for launch slips, mission failures, and contributing to major project cost growth.  Estimation errors resulting in software cost growth rates of 50 percent to over 100 percent are typically identified as a contributing factor in post-development lessons learned.  Barry Boehm's seminal chart shown below captures one of the main reasons why estimation is difficult. The figure illustrates that estimation uncertainty is so large in the early stages of the life cycle, that estimates can be off by a factor of four.

Fortunately, 30 years of cost estimation and modeling research and practice have identified methods for addressing these known issues.  These are reflected in the process described in this requirement.

Software cost estimates are a key activity performed as part of software life-cycle planning (NPR 7150.2, Section 3.1) with regular updates made throughout the entire lifecycle.  This activity is performed as a part of software tasks of all sizes and all classes with the primary difference being the level of detail and amount of review of the estimates.  Two software cost estimates are required for software class A and B projects with an estimated project cost of 2 million dollars or more.  Two estimates are also recommended when the project scope is not well understood.

 It is highly recommended that model-based and analogy estimates be completed as verification or backup to the primary estimate, which is typically a bottom-up estimate.  Multiple estimates are especially important due to the extensive estimation uncertainty that exists in the early part of the lifecycle.  Most models provide a method for expressing the estimated uncertainty that the project team can use as part of the basis of the estimate. 

The key elements of the process are the development of the following:

  • Two estimates, one of which is a model-based estimate.
  • A software size estimate and other key planning parameters.
  • A risk list with mitigations (SWE-151).
  • A documented basis of estimate (BOE) that can be revised as plans are updated.

Scope of the Job

The project team should determine the scope of the software task, including what the task is and is not, and what it covers. When the project manager collaborates with the Center project and cost offices to generate cost estimates, the results of scoping the work is a key input from the project. 

Panel

Scoping is not requirements writing – requirements are generally developed after the initial planning and estimating are completed.

The goal is to identify clearly and in sufficient detail the entire set of software products and activities for producing a good cost estimate.  This includes understanding the intended concept of operations and operating environment to fully characterize the complexity of the work. The project team also identifies values for key planning parameters, including the systems schedule, risk posture, new technology assumptions, expected inheritance, and complexity.

Typically, the scope of a software development effort includes all activities associated with software management, software engineering, programming, and software test engineering over the software life cycle. Included in this effort are software requirements analysis, software design, software implementation, and software integration and testing.  

Bottom-Up Estimate

When developing the bottom-up cost estimate, whether at the project level or in conjunction with the appropriate Center offices, the first step is to develop the work breakdown structure (WBS).  A critical aspect of developing the WBS is ensuring that it is easily mapped to other key task breakdowns, including the functional or object decomposition and schedule elements.  It is important to be able to quickly modify the cost, schedule, and functional design as changes occur to keep them consistent.

A recommended sequence of steps for the bottom-up estimate is the following.

  • Define a WBS.
  • Estimate size and/or effort for each element.
  • If available, map analogous size, effort, and/or costs into the current WBS.
  • Adjust the baseline for your mission and document how and why it was adjusted as part of the bottom-up estimate.
  • Lay the estimate out over time.
  • Use an approved tool to get costs.
  • Use reference data to assist in an effort estimate or to check the distribution of effort.

Estimate Software Size

Software size is a required input for the use of a cost model and can also be used as part of a bottom-up estimate.  Estimating software size is one of the most complicated estimation activities. Software size can be measured in various ways but the most common measure is to count lines of code (LOC).  The most used LOC metrics are physical lines (carriage returns excluding comments and blanks) and logical lines, which count logical delimiters such as terminal semi-colons in C along with preprocessor directives and terminal close-braces.  The accuracy of size estimate is greatly improved when anchored by actual code counts from similar software products or similar software components, which require a code counter such as Source Lines Counter (SLiC), found on the NASA Software PAL (See the

Tablink
05
1Resources tab
tab5
linktextResources Tab
). It is also required to distinguish between new, reused, and modified-reused code as the cost of developing code is very different for each type of code. 

A common estimation mistake is the overestimation of cost savings when reused and modified-reused software is included in a system.  Care should be taken not to overestimate the amount of reused code or underestimate the effort to modify that code for use in the system.  Incorporating reused code requires the developer to do more than just testing and may not necessarily result in significant cost savings.  An assessment of the code may be needed to determine how much code can be used in the new system.  Code modification is necessary and that effort is affected by several factors including how effectively the code can be understood (i.e., how well it is commented, how well it is structured, etc.), the amount of documentation that exists for the reused code, whether the code was designed for reuse, etc. 

Floatbox

One recommendation is that if the reused code will require greater than 50 percent modifications, then it should be treated as a new code for cost estimation purposes.

For more information and a detailed description of how to handle the different types of code, consult Software Engineering Economics, by Boehm

Swerefn
refnum136
, Software Cost Estimation with COCOMO II, by Boehm, et. al.
Swerefn
refnum135
, and the Handbook for Software Cost Estimation by Lum, et. al., (accessible to NASA users in Software Processes Across NASA (SPAN) from the SPAN tab in this Handbook). Other methods that can be used to estimate the software size include function point and use case counting.

Model-Based Estimates

Model-based estimates are estimates made using parametric cost models. Parametric cost models have been in use at NASA for over 20 years.  The two most used parametric software cost models are COCOMOTM II and SEER®-SEM.  The Software COCOMO™ Analysis Tool (SCAT)  is a probabilistic version of COCOMOTM II and can be found on the NASA Software PAL. (Refer to the 

Tablink
05
1Resources tab
tab5
linktextResources Tab
for additional information on these tools.) Cost models can be used as a primary estimate early in the life cycle, as a secondary backup estimate for validation, and to help you reason about the cost and schedule implications of software decisions you may need to make. 

Cost models require an estimate of the size of the system and a set of inputs describing the system and development environment; these items are referred to as cost drivers or effort multipliers.  

Panel

Effort multipliers characterize the product, platform, personnel, and project attributes of the software project under development.

As an example, COCOMOTM II has 17 effort multipliers. Each of the COCOMOTM parameters is associated with up to six ratings – “very low,” “low,” “nominal,” “high,” “very high,” and “extra high”, which correspond to a real number based upon the factor and the degree to which the factor can influence productivity.  A rating equal to 1 does not increase nor decrease the schedule and effort (this rating is called “nominal”). A rating of less than 1 denotes a factor that can decrease the schedule and effort.  A rating greater than 1 denotes a factor that increases the schedule or effort.  For a detailed description of the COCOMOTM model and the user guides for the commercial cost models, consult Software Engineering Economics, by Boehm

Swerefn
refnum136
, Software Cost Estimation with COCOMO II, by Boehm, et. al.
Swerefn
refnum135
, and the Handbook for Software Cost Estimation by Lum, et. al. accessible to NASA users in SPAN.

Validation and Reconciliation

The purpose of this step is to review the validated estimates concerning the project-imposed budget and schedule and to resolve the differences. If an inconsistency arises, there is a tendency to incorrectly address the issue as only a problem of incorrect estimation. However, in most cases, the real solution is to reduce scope or functionality, and then to reduce scope again, until the task fits the budget. This step is another area where the project can provide valuable input to Center costing offices since the project team has the best understanding of the work to be performed. 

Panel

Do not reduce costs by eliminating reserves and making optimistic and unrealistic assumptions, especially concerning the amount of code inheritance.

Review, Approve and Maintain the Estimates

The purpose of this step is to review the software estimates and to obtain stakeholder approval.

The project team should conduct a peer review with the following objectives:

  • Confirm the scope and Work Breakdown Structure (WBS) are complete and accurate.
  • Verify the methods used for deriving the size, effort, schedule, and cost. • Ensure the assumptions and input data used to develop the estimates are captured in the cost models and are correct, • Ensure that the estimates are reasonable and accurate, given the input data.
  • Formally confirm and record the approved software estimates and underlying assumptions for the project.

The stakeholders, which include the software manager, software estimators, line management, and project management, approve the software estimates after the review is complete and problems have been resolved. Remember that costs cannot be reduced without reducing functionality.

The approved software estimates and supporting information such as the BOE should be configuration managed in a location accessible to stakeholders.  The estimates should be updated in response to changes in schedule, budget, technical scope, development methodology, personnel, or other factors that could alter the accuracy of the approved estimates.

If the project has a cost repository, that repository should be updated with data related to this cost estimate, including software size, effort, and schedule data.

NASA-specific cost estimation process information is available in Software Processes Across NASA (SPAN), accessible to NASA users from the SPAN tab in this Handbook. 

Additional guidance related to software cost estimation may be found in the following related requirements in this Handbook:

Div
idtabs-4

4. Small Projects

The basic estimation techniques apply to small as well as large tasks but they are tailored or scaled to fit the size and scope of the task. One area of concern is with the cost models, as they tend to be calibrated to medium size and larger projects. It is recommended that a greater reliance be placed upon analogy-based cost estimates unless the model being used can be verified for use on small tasks in your local environment.

Div
idtabs-5

5. Resources

5.1 References

refstable
Show If
groupconfluence-users
Panel
titleColorred
titleVisible to editors only

Enter the necessary modifications to be made in the table below:

SWEREFs to be addedSWEREFS to be deleted


SWEREFs called out in the text: 135.136, 419, 567

SWEREFs NOT called out in text but listed as germane: 116, 166, 184, 306, 461

5.2 Tools


Include Page
Tools Table Statement
Tools Table Statement


Div
idtabs-6

6. Lessons Learned

6.1 NASA Lessons Learned

The NASA Lessons Learned database contains the following lessons learned related to cost estimation:

  • Know-How Your Software Measurement Data Will Be Used. Lesson Number 1772
    Swerefn
    refnum567
    :
    When software measurement data used to support cost estimates is provided to NASA by a project without an understanding of how NASA will apply the data, discrepancies may produce erroneous cost estimates that disrupt the process of project assessment and approval. Major flight projects should verify how NASA plans to interpret such data and use it in their parametric cost estimating model, and consider duplicating the NASA process using the same or a similar model before submission.

6.2 Other Lessons Learned

  • Other Lessons Learned from experience (Hihn, Jairus M. JPL. 818.354.1248) and the JPL Cost Estimation Handbook include the following concepts:
    • Keep your history.
      • Keep the basis of estimates (BOE) and cost data to support future analogies.
      • Keep data on your estimation vs. actual performance.
      • For incremental deliveries, the best data you have is what it took to get the job done on the earlier deliveries.
    • When the budget is cut, descope the effort.
    • When in sales mode, there is tremendous pressure to be optimistic about the cost and capability to sell the job.
    • Budget 'bogies' get set very early in the life cycle. Sometimes based on casual conversations.
      • You will typically get held to this number!
    • Software estimation is fundamentally an uncertain business under the best of conditions.
    • Common causes of cost growth. Historically, there is a pattern of being overly optimistic in cost estimates by not taking sufficient account for the following:
      • Changes and increases in scope.
      • Concurrent hardware development.
      • Inability to scope software functionality due to inadequate project definition.
      • Software is used for risk mitigation, but never planned for upfront.
      • Software is the system complexity sponge.
      • Test Bed and simulator development, availability, and maturity.
      • Optimistic software inheritance assumptions.
      • Anything new or being done for the first time.
      • Developing Technologies.
      • Autonomy.
      • Precision landing.
      • Hazard avoidance.
      • Design.
      • Language.
      • Tools.
      • Development environment.
      • Processes.
      • Customer or sponsor-initiated changes.


  • In addition to these Lessons Learned, Chapter 12 of the GAO Cost Estimating and Assessment Guide, Best Practices for Developing and Managing Capital Program Costs (GAO-09-3SP)
    Swerefn
    refnum419
    , discusses problems with underestimating software costs, including this excerpt from a case study, "The original estimate for the Space-Based Infrared System for nonrecurring engineering, based on experience in legacy sensor development and assumed software reuse, was significantly underestimated. Nonrecurring costs should have been two to three times higher, according to historical data and independent cost estimators. Program officials also planned on savings from simply rehosting existing legacy software, but those savings were not realized because all the software was eventually rewritten. It took 2 years longer than planned to complete the first increment of software."
Div
idtabs-7

7. Software Assurance

Excerpt Include
SWE-015 - Cost Estimation
SWE-015 - Cost Estimation

7.1 Tasking for Software Assurance

1. Confirm that the required number of software cost estimates are complete and include software assurance cost estimate(s) for the project, including a cost estimate associated with handling safety-critical software and safety-critical data.

7.2 Software Assurance Products

  • The cost estimate for the project’s software assurance and safety support.


    Note
    titleObjective Evidence
    • Evidence of confirmation that the correct number of cost estimates are complete, including any issues or risks, identified.
    Expand
    titleDefinition of objective evidence

    Include Page
    SITE:Definition of Objective Evidence
    SITE:Definition of Objective Evidence

7.3 Metrics

  • Planned SA resource allocation versus actual SA resource allocation.
  • Comparison of initial SA cost estimates vs. final cost (capturing assumptions and differences)

7.4 Guidance

Confirm that the required number of software cost estimates are complete.

  • Two cost estimate models and associated cost parameters for all Class A and B software projects that have an estimated project cost of $2 million or more.
  • One software cost estimate model and associated cost parameter(s) for all Class A and Class B software projects that have an estimated project cost of less than $2 million.
  • One software cost estimate model and associated cost parameter(s) for all C and D software projects.
  • One software cost estimate model and associated cost parameter(s) for all Class F software projects.

Confirm that the required number of software cost estimates are complete - Obtain the cost estimate(s) from the project or access them in their repository.  Confirm the project generated the correct number of estimates based on SWE-015. Inform the project if a cost estimate is missing and track to closure the resolution to this missing information.

Develop a software assurance cost estimate for the project, including cost estimation associated with handling safety-critical software - Determine if the SA and Software Safety costs are included in the project's software cost estimate. The general rule of thumb is that Software Assurance costs should be between 5 and 6% of the overall software estimated cost.  If the SA and Software Safety costs are not included, work with the project to update the cost estimate to include or reference the SA-generated cost estimate for the project.

Confirm the cost estimate satisfies the conditions in SWE-151.

Covers the entire software life cycle.

It is based on selected project attributes (e.g., assessment of the size, functionality, complexity, criticality, reuse code, modified code, and risk of the software processes and products).

It is based on the cost implications of the technology to be used and the required maturation of that technology.

Incorporates risk and uncertainty, including cybersecurity.

Includes the cost of the required software assurance support.

Includes other direct costs.

Confirm the cost estimate satisfies the conditions in SWE-151 - Confirm that the project cost estimate(s) contains all of the required information per SWE-151. Track to closure with the project any missing information.