This is the table from Topic 8.18, reformatted a little but without TABSETUP and other things that might break sticky headers. It doesn't have sticky headers and I don't know why.
Metrics Type | Measurements | PLAN | REQ | DES | IMP | TEST | DEL | Associated SWE Reqt # |
---|---|---|---|---|---|---|---|---|
Peer Review Metrics | # of peer reviews performed vs. # of peer reviews planned | X | X | X | X | X | SWE-016 SWE-087 SWE-089 | |
Peer Review Metrics | # of Non-Conformances identified in each peer review | X | X | X | X | X | SWE-087 SWE-089 | |
Peer Review Metrics | # of Non-Conformances identified by software assurance during each peer review | X | X | X | X | X | SWE-087 SWE-088 SWE-089 | |
Peer Review Metrics | Total # of peer review Non-Conformances (Open, Closed) | X | X | X | X | X | SWE-087 SWE-088 SWE-089 | |
Peer Review Metrics | Preparation time each review participant spent preparing for the review | X | X | X | X | X | SWE-088 SWE-089 | |
Peer Review Metrics | Time required to close review Non-Conformances | X | X | X | X | X | SWE-087 SWE-088 SWE-089 | |
Peer Review Metrics | # of peer review participants vs. total # invited | X | X | X | X | X | SWE-088 SWE-089 | |
Peer Review Metrics | # of peer review Non-Conformances per work product vs. # of peer reviewers | X | X | X | X | X | SWE-088 SWE-089 | |
Peer Review Audit Metrics | # of audit Non-Conformances per peer review audit | X | X | X | X | X | SWE-088 | |
Peer Review Audit Metrics | # of Peer Review Audits planned vs. # of Peer Review Audits performed | X | X | X | X | X | SWE-016 SWE-087 SWE-088 | |
Peer Review Audit Metrics | Trends on non-conformances from audits (Open, Closed, Life cycle Phase) | X | X | X | X | X | SWE-088 SWE-089 | |
Peer Review Audit Metrics | Time required to close peer review audit Non-Conformances | X | X | X | X | X | SWE-088 SWE-089 | |
Peer Review Audit Metrics | Preparation time each audit participant spent preparing for audit | X | X | X | X | X | SWE-088 SWE-089 | |
Problem/Change Report Status Metrics | Total # of Non-Conformances over time (Open, Closed, # of days Open, and Severity of Open) # of Non-Conformances in current reporting period (Open, Closed, Severity) | X | X | X | X | X | X | SWE-062 SWE-065c SWE-065d SWE-068 SWE-202 SWE-203 SWE-204 |
Problem/Change Report Status Metrics | # of safety-related Non-Conformances | X | X | X | X | X | SWE-203 SWE-068 SWE-071 | |
Problem/Change Report Status Metrics | Trend of Open vs. Closed Non-Conformances over time | X | X | X | X | X | X | SWE-053 SWE-054 SWE-065 |
Problem/Change Report Status Metrics | Trend of change status over time (# of changes approved, # in implementation, # in test, # closed) | X | X | X | X | X | X | SWE-018 SWE-053 SWE-080 |
Problem/Change Report Status Metrics | # of Non-Conformances identified in embedded COTS, GOT, MOTS, OSS, or reused components in ground or flight software vs. # of Non-Conformances closed | X | X | X | SWE-136 SWE-202 SWE-203 SWE-211 | |||
Problem/Change Report Status Metrics | # of Non-Conformances identified in source code products used (Open, Closed) | X | X | X | SWE-202 SWE-203 | |||
Problem/Change Report Status Metrics | # of software Non-Conformances at each Severity level for each software configuration item (Open, Closed) Bold type indicates a required item |
|
|
| X | X | X | SWE-202 |
Problem/Change Report Status Metrics | # of Closed action items vs. # of Open action items | X | X | X | X | X | X | SWE-062 SWE-62c SWE-065d |
Problem/Change Report Status Metrics | # of Root Cause Analyses performed; # of Non-Conformances identified by each root cause analysis | X | X | X | X | SWE-204 | ||
SA Corrective Action (CA) metrics (Issues, Risks) | # of Corrective Actions (CAs) raised by SA vs. total # Attributes (Type, Severity, # of days Open, Life cycle Phase Found) State (Open, In work, Closed) Trends of CA Open vs. Closures over time | X | X | X | X | X | X | SWE-024 SWE-204 SWE-054 |
SA Corrective Action (CA) metrics (Issues, Risks) | Trend the # of inconsistencies or corrective actions identified, and # closed. | X | X | X | X | X | SWE-054 SWE-024 SWE-204 | |
SA Corrective Action (CA) metrics (Issues, Risks) | # of open vs. closed issues over time and latency | X | X | X | X | X | X | SWE-018 |
Process Improvement Metrics | # of software work product Non-Conformances identified by life cycle phase over time | X | X | X | X | X | X | SWE-013 SWE-022 SWE-024 SWE-039 SWE-051 SWE-054 SWE-057 SWE-058 SWE-062 SWE-065b SWE-065c SWE-065d SWE-068 SWE-071 SWE-075 SWE-079 SWE-084 SWE-086 SWE-087 SWE-125 SWE-134 SWE-139 SWE-146 SWE-157 SWE-159 SWE-184 SWE-185 SWE-187 SWE-191 SWE-194 SWE-201 SWE-204 SWE-205 |
Process Improvement Metrics | # of software process Non-Conformances by life cycle phase over time | X | X | X | X | X | X | SWE-032 SWE-039 SWE-061 SWE-077 SWE-080 SWE-082 SWE-085 SWE-086 SWE-088 SWE-139 SWE-195 SWE-204 |
Process Improvement Metrics | Identify the specific requirements in NASA-STD-8739.8 that are being tailored by the projects (*organizational metric) | X | X | X | X | X | X | SWE-121 SWE-125 SWE-013 SWE-176 |
Process Improvement Metrics | # of projects tailoring each requirement (*organizational measure) % of requirements tailored per project (*organizational measure) | X | X | X | X | SWE-125 SWE-013 SWE-121 | ||
Process Improvement Metrics | % of Total Source Code for each Software Classification (*organizational measure) | X | X | X | SWE-020 SWE-176 SWE-087 | |||
Cost/ Effort Metrics | Planned SA resource allocation vs. actual SA resource allocation | X | X | X | X | X | X | SWE-015 SWE-174 SWE-151 |
Cost/ Effort Metrics | Comparison of initial SA cost estimates vs. final cost (capturing assumptions and differences) | X | X | SWE-174 SWE-015 SWE-151 | ||||
Cost/ Effort Metrics | Trend SA cost estimates throughout life cycle | X | X | X | X | X | X | SWE-174 |
Training Metrics | % of required training completed for each of the project SA personnel | X | X | X | X | SWE-017 | ||
Training Metrics | % of project personnel that have completed project specific training against the planned training schedule | X | X | X | X | X | SWE-017 | |
Compliance Audit Metrics | # of Compliance Audits planned vs. # of Compliance Audits performed | X | X | X | X | X | X | SWE-024 SWE-039 SWE-139 SWE-016 SWE-032 SWE-077 SWE-195 SWE-082 SWE-084 SWE-085 SWE-086 SWE-088 SWE-079 SWE-201 |
Compliance Audit Metrics | # of Open vs. Closed Audit Non-Conformances over time # of Non-Conformances per audit (including findings from process and compliance audits, process maturity) | X | X | X | X | X | X | SWE-022 SWE-024 SWE-039 SWE-139 SWE-016 SWE-032 SWE-077 SWE-079 SWE-195 SWE-082 SWE-084 SWE-085 SWE-086 SWE-088 SWE-201 |
Compliance Audit Metrics | # of Non-Conformances identified in plans (e.g., SMPs, SDPs, CM Plans, SA Plans, Safety Plans, Test Plans) | X | X | X | X | X | SWE-024 SWE-013 SWE-075 SWE-079 SWE-139 SWE-071 | |
Compliance Audit Metrics | # of Non-Conformances identified in the software Configuration Management Plan Trends of # Open vs. # Closed over time | X | X | X | X | X | SWE-079 | |
Compliance Audit Metrics | # of Configuration Management Audits conducted by the project – Planned vs. Actual | X | X | X | X | X | SWE-082 SWE-077 SWE-084 | |
Compliance Audit Metrics | # of Non-Conformances per audit (including findings from process and compliance audits, process maturity) | X | X | X | X | X | X | SWE-024 SWE-039 SWE-139 SWE-016 SWE-032 SWE-077 SWE-195 SWE-082 SWE-084 SWE-085 SWE-086 SWE-088 SWE-079 |
Compliance Audit Metrics | # of process Non-Conformances (e.g., activities not performed) identified by SA vs. # accepted by the project Trends of # Open vs. # Closed over time | X | X | X | X | X | X | SWE-016 SWE-039 SWE-032 SWE-077 SWE-195 SWE-082 SWE-084 SWE-085 SWE-086 SWE-088 |
Compliance Audit Metrics | # of Non-Conformances found in flight code, ground code, tools, and COTs products used (Open vs. Closed). | X | X | X | X | SWE-136 | ||
Compliance Audit Metrics | # of open non-compliances vs. # of closed non-compliances found in security scans or coding standard compliance audits. | X | X | X | X | SWE-63 | ||
Project Acceptance Metrics | # of Non-Conformances (activities not being performed) # of Non-Conformances accepted by project # of Non-Conformances (Open, Closed, Total) Trends of Open vs, Closed Non-Conformances over time | X | X | X | X | X | X | SWE-087 SWE-201 SWE-039 SWE-139 |
Progress Tracking Metrics | Deviations of actual schedule progress vs. planned schedule progress above defined threshold | X | X | X | X | X | X | SWE-016 SWE-018 SWE-046 |
Progress Tracking Metrics | # of Software Requirements (e.g. Project, Application, Subsystem, System, etc.) | X | X | X | X | X | SWE-050 SWE-051 SWE-052 SWE-065b SWE-066 SWE-194 SWE-027 | |
Progress Tracking Metrics | # of Software Requirements that do not trace to a parent requirement | X | X | X | SWE-033 SWE-050 SWE-051 | |||
Progress Tracking Metrics | # of architectural issues identified vs. number closed | X | SWE-057 SWE-058 SWE-143 | |||||
Progress Tracking Metrics | # of planned units for implementation vs. # of units tested and implemented | X | SWE-060 | |||||
Progress Tracking Metrics | # of planned unit test cases vs. # of actual unit test cases completed | X | SWE-062 SWE-186 | |||||
Progress Tracking Metrics | Total # of tests completed vs. # of test results evaluated and signed off | X | X | SWE-066 SWE-068 SWE-065d SWE-159 | ||||
Progress Tracking Metrics | # of Safety-Critical tests executed vs. # of Safety-Critical tests witnessed by SA | X | X | X | SWE-066 SWE-068 SWE-065d SWE-159 SWE-062 SWE-186 | |||
Progress Tracking Metrics | # of software components (e.g. programs, modules, routines, functions, etc.) planned vs. # actually released in each build | X | X | SWE-194 SWE-077 SWE-073 SWE-036 | ||||
Progress Tracking Metrics | # of Non-Conformances from reviews (Open vs. Closed; # of days Open) | X | X | X | X | X | X | SWE-134 SWE-037 SWE-039 SWE-087 SWE-088 SWE-089 SWE-143 |
Progress Tracking Metrics | # of Software Requirements being met via satisfactory testing vs. total # of Software Requirements | X | X | X | SWE-065d SWE-066 SWE-192 SWE-071 | |||
Progress Tracking Metrics | # of Software Requirements without associated test cases | X | X | X | SWE-066 SWE-065b SWE-071 | |||
Progress Tracking Metrics | # of design issues found vs. # of design issues resolved | X | X | SWE-058 | ||||
Progress Tracking Metrics | # of planned units for implementation vs. # of units implemented and unit tested. | X | X | X | SWE-060 | |||
Risk Management Metrics | # of Risks identified in each life cycle phase (Open, Closed) | X | X | X | X | X | X | SWE-086 SWE-039 SWE-179 SWE-154 SWE-156 SWE-190 |
Risk Management Metrics | # of Risks by Severity (e.g., red, yellow, green) over time | X | X | X | X | X | X | SWE-032 SWE-033 SWE-039 SWE-086 SWE-154 SWE-156 SWE-179 SWE-190 SWE-191 |
Risk Management Metrics | # of Risks with mitigation plans vs. total # of Risks | X | X | X | X | X | X | SWE-032 SWE-033 SWE-039 SWE-086 SWE-154 SWE-156 SWE-179 SWE-190 SWE-191 |
Risk Management Metrics | # of Risks trending up over time # of Risks trending down over time | X | X | X | X | X | X | SWE-032 SWE-033 SWE-039 SWE-086 SWE-154 SWE-156 SWE-179 SWE-190 SWE-191 |
Cybersecurity Risk Metrics | # of Cybersecurity Risks identified (Open, Closed, Severity) | X | X | X | X | SWE-154 SWE-156 | ||
Cybersecurity Risk Metrics | ·of Cybersecurity Risks with Mitigations vs. # of Cybersecurity Risks identified | X | X | X | X | SWE-154 SWE-156 SWE-159 | ||
Traceability Metrics | % of traceability completed in each area: System Level requirements to Software requirements; Software Requirements to Design; Design to Code; Software Requirements to Test Procedures | X | X | X | X | SWE-052 | ||
Traceability Metrics | % of traceability completed for all hazards to software requirements and test procedures | X | X | X | X | SWE-052 | ||
Traceability Metrics | Defect trends for trace quality (# of circular traces, orphans, widows, etc.) | X | SWE-051 SWE-052 | |||||
Requirements Metrics | # of detailed software requirements vs. # of estimated SLOC to be developed by the project | X | X | X | SWE-050 SWE-051 SWE-151 SWE-174 | |||
Requirements Metrics | # of incorrect, missing and incomplete requirements (i.e., # of requirements issues) vs. # of requirements issues resolved | X | X | SWE-051 SWE-053 SWE-054 | ||||
Requirements Metrics | Software Requirements Volatility (# of requirements added, deleted, modified, # of TBDs over time) |
| X | X | X | X |
| SWE-200 SWE-053 |
Requirements Metrics | # of TBD/TBC/TBR requirements trended over time |
|
| X | X | X | X | SWE-066 |
Safety Metrics | # of safety-related requirement issues (Open, Closed) over time | X | X | X | X | X | SWE-039 SWE-139 SWE-205 SWE-023 SWE-134 SWE-184 SWE-052 SWE-051 SWE-058 SWE-065b SWE-066 SWE-071 SWE-192 SWE-080 SWE-087 | |
Safety Metrics | # of safety-related non-conformances identified by life cycle phase (over time, Open vs. Closed, # of days) | X | X | X | X | X | SWE-013 SWE-039 SWE-139 SWE-143 SWE-121 SWE-184 SWE-023 SWE-134 SWE-052 SWE-051 SWE-057 SWE-058 SWE-135 SWE-062 SWE-065a SWE-065b SWE-065c SWE-065d SWE-066 SWE-068 SWE-071 SWE-191 SWE-080 SWE-081 SWE-087 SWE-205 | |
Reuse Metrics | # of products submitted for reuse; # of developed products submitted for reuse vs. total # of developed products | X | SWE-147 SWE-148 | |||||
Reuse Metrics | # of developed products entered in NASA Internal Sharing & Reuse System vs. total # of developed products | X | SWE-147 SWE-148 | |||||
Reuse Metrics | # of products submitted for reuse vs. # of products entered into NASA Internal Sharing & Reuse Systems | X | SWE-147 SWE-148 | |||||
Cybersecurity Metrics | # of Cybersecurity vulnerabilities and weaknesses identified # of Cybersecurity vulnerabilities and weaknesses (Open, Closed, Severity) Trending of Open vs. Closed over time | X | X | X | X | X | X | SWE-159 SWE-135 SWE-063 |
Cybersecurity Metrics | # and type of vulnerabilities and weaknesses identified by the project | X | X | X | X | X | SWE-135 SWE-063 | |
Cybersecurity Metrics | # of Cybersecurity vulnerabilities and weaknesses identified by life cycle phase | X | X | X | X | X | SWE-159 SWE-135 SWE-063 | |
Cybersecurity Metrics | # of Cybersecurity vulnerabilities and weaknesses identified vs. # resolved during Implementation | X | X | X | SWE-159 SWE-135 SWE-063 | |||
Cybersecurity Metrics | # of requirements specified relating to detection of adversarial actions vs. # of requirements related to detection of adversarial actions actually implemented | X | X | X | SWE-210 | |||
Cybersecurity Metrics | # of Non-Conformances identified in Cybersecurity coding standard compliance (Open, Closed) | X | X | X | SWE-063 SWE-135 SWE-207 | |||
Test Coverage Metrics | Software code/test coverage percentages for all identified safety-critical components (e.g., # of paths tested vs. total # of possible paths) Note: Metrics in bold type are required by all projects | X | SWE-066 | |||||
Test Coverage Metrics | Test coverage data for all identified safety-critical software components. | X | SWE-219 | |||||
Test Coverage Metrics | % of code that has been executed during testing | X | SWE-060 | |||||
Static Code Metrics | Document the Static Code Analysis tools used with associated Non-Conformances ·of total errors and warnings identified by the tool # of errors and warnings evaluated vs. # of total errors and warnings identified by the tool | X | SWE-135 SWE-185 | |||||
Static Code Metrics | # of Non-Conformances raised by SA vs. total # of raised Non-Conformances | X | SWE-135 SWE-185 | |||||
Static Code Metrics | # of static code errors and warnings identified as “positives” vs. # of total errors and warnings identified by the tool Total # of static code analysis "positives" vs. # of "positives" resolved. Trend over time. # of static code errors and warnings resolved by Severity vs. # of static code errors and warnings identified by Severity by the tool | X | SWE-135 SWE-185 | |||||
Static Code Metrics | # of static code “positives” over time (Open, Closed, Severity) | X | X | SWE-135 SWE-185 | ||||
Static Code Metrics | # of Cybersecurity vulnerabilities and weaknesses identified by the tool | X | X | SWE-135 SWE-185 | ||||
Static Code Metrics | # of coding standard violations identified (Open, Closed, type of violation, Severity) | X | SWE-061 SWE-185 | |||||
Static Code Metrics | Software cyclomatic complexity # for all identified safety-critical components | X | X | SWE-087 SWE-134 | ||||
Static Code Metrics | Trend of # of total errors and warnings identified per SCA Tool, Language, and SLOC size | X | SWE-135 | |||||
Static Code Metrics | Total # of static code analysis "positives" vs. # of "positives" resolved. Trend over time. | X | SWE-135 | |||||
Test Procedures Metrics | # of Non-Conformances and risks open vs. # of Non-Conformances, risks, identified with test procedures | X | X | SWE-087 SWE-065b SWE-071 SWE-191 | ||||
Test Procedures Metrics | # of hazards with completed test procedures/cases vs. total number of hazards over time | X | X | SWE-065b SWE-068 SWE-191 | ||||
Test Procedures Metrics | # of software requirements with completed test procedures/cases over time | X | X | SWE-065b SWE-071 SWE-066 | ||||
Test Procedures Metrics | # of Non-Conformances identified when the approved, updated requirements are not reflected in test procedures | X | X | SWE-065b SWE-071 SWE-052 SWE-066 SWE-191 | ||||
Test Procedures Metrics | # of Non-Conformances identified while confirming hazard controls are verified through test plans/procedures/cases | X | X | SWE-065b SWE-071 SWE-066 SWE-068 SWE-191 | ||||
Test Procedures Metrics | # of issues and risks/corrective actions open vs. total # of issues and risks/corrective actions identified with test procedures | X | X | X | SWE-065b | |||
Test Metrics | # of tests executed vs. # of tests completed | X | X | X | SWE-062 SWE-066 SWE-065d SWE-068 SWE-159 SWE-190 SWE-192 SWE-055 SWE-080 SWE-191 SWE-194 SWE-211 | |||
Test Metrics | # of Non-Conformances identified during each testing phase (Open, Closed, Severity) | X | X | X | SWE-062 SWE-065d SWE-066 SWE-068 SWE-080 SWE-159 SWE-190 SWE-191 SWE-192 SWE-194 SWE-211 | |||
Test Metrics | ·of Requirements tested vs. total # of Requirements | X | X | X | SWE-062 SWE-065b SWE-065d SWE-066 SWE-080 SWE-191 SWE-192 SWE-194 | |||
Test Metrics | # of Hazards containing software that have been tested vs. total # of Hazards containing software | X | X | X | SWE-062 SWE-066 SWE-068 SWE-080 SWE-134 SWE-192 SWE-205 | |||
Test Metrics | # of Non-Conformances identified in models, simulations, and tools over time (Open, Closed, Severity) | X | X | X | SWE-070 | |||
Test Metrics | # of Regression test set Non-Conformances/Risks over time (Open, Closed, Severity) | X | X | X | SWE-191 | |||
Test Metrics | # of risks and Non-conformances open vs. total # of risks and Non-Conformances identified with test code | X | X | X | SWE-065c | |||
Test Metrics | # of Requirements tested in customer environment vs. # of Requirements | X | X | SWE-055 | ||||
Cybersecurity Metrics During Testing Metrics | # of Cybersecurity mitigation implementations identified from the security vulnerabilities and security weaknesses | X | X | X | SWE-154 SWE-159 SWE-191 | |||
Cybersecurity Metrics During Testing Metrics | # of Cybersecurity mitigation implementations identified with associated test procedures vs. # of Cybersecurity mitigation implementations identified | X | X | X | SWE-154 SWE-159 SWE-191 | |||
Cybersecurity Metrics During Testing Metrics | # of Cybersecurity mitigation tests completed vs. total # of Cybersecurity mitigation tests | X | X | X | SWE-159 | |||
Cybersecurity Metrics During Testing Metrics | # of Non-Conformances identified during Cybersecurity mitigation testing (Open, Closed, Severity) | X | X | X | SWE-159 | |||
Cybersecurity Metrics During Testing Metrics | Trends of Cybersecurity Non-Conformances over time | X | X | X | SWE-159 SWE-063 SWE-135 SWE-201 | |||
Test Coverage Metrics | Software code/test coverage percentages for all identified safety-critical components (e.g., # of paths tested vs. total # of possible paths) |
|
|
| X | X | X | SWE-066 SWE-190 SWE-134 SWE-189 |
Test Coverage Metrics | # of tests completed vs. total # of tests | X | X | X | SWE-055 SWE-062 SWE-066 SWE-065d SWE-068 SWE-080 SWE-159 SWE-190 SWE-191 SWE-192 SWE-194 SWE-211 | |||
Test Coverage Metrics | # of detailed software requirements tested to date vs. total # of detailed software requirements | X | X | X | SWE-055 SWE-062 SWE-065b SWE-065d SWE-066 SWE-071 SWE-080 SWE-191 SWE-192 SWE-194 SWE-159 | |||
Test Coverage Metrics | # of safety-critical requirement verifications vs. total # of safety-critical requirement verifications completed # of Open issues vs. # of Closed over time | X | X | X | SWE-062 SWE-066 SWE-191 SWE-192 SWE-068 | |||
Test Coverage Metrics | # of Source Lines of Code (SLOC) tested vs. total # of SLOC | X | X | X | SWE-066 SWE-134 SWE-189 SWE-190 SWE-219 | |||
Build/Release Content Metrics | # of software units planned vs. # actually built | X | X | X | X | SWE-063 SWE-194 | ||
Build/Release Content Metrics | # of planned software requirements implemented in each build vs. # of actual software requirements implemented in each build | X | X | X | SWE-063 SWE-194 | |||
Build/Release Content Metrics | # of Non-Conformances identified in release documentation (Open, Closed) | X | X | X | SWE-063 SWE-077 SWE-084 SWE-085 | |||
Operations/ Maintenance Metrics | # of Non-Conformances identified in the software after delivery | X | SWE-195 | |||||
Other Metrics | Measures relating to status and performance as identified in other requirements. (Schedule deviations, closure of corrective actions, product and process audit results, peer review result, etc) | X | X | X | X | SWE-093 | ||
Other Metrics | # of requirements being met, any TBD/TBC/TBR requirements, or any requirements that are not being met Performance and functionality measures (Schedule deviations, closure of corrective actions, product and process audit results, peer review results, requirements volatility, # of requirements satisfactorily tested vs. total # of requirements, etc.) | X | X | X | X | SWE-199 | ||
Other Metrics | # of findings open vs. # of findings identified | X | X | X | X | X | SWE-082 | |
Other Metrics | Trends of Open vs. Closed Non-Conformances change reports over time. | X | X | X | X | X | SWE-065d | |
IV&V Metrics (Kept by IV&V) | # of IV&V Non-Conformances/issues,/risks (Open, Closed, accepted by the project, severity, category of Non-Conformance (e.g., requirements severity, category (requirements, design, code, test, documentation, etc.)) Kept by IV&V team, not SA | X | X | X | X | X | X | SWE-179 |
Coverage Metrics | Code coverage data: % of code that has been executed during testing | X | X | X | SWE-060 | |||
Coverage Metrics | Test coverage data for all identified safety-critical software components. | X | X | X | SWE-219 |
Old
...
Metrics Type
...
Measurements
...
Plan
...
Reqt
...
Des
...
Imp
...
Test
...
Del
...
Associated SWE Reqt #
...
Peer Review Metrics
...
# of peer reviews performed vs. # of peer reviews planned
...
X
...
X
...
X
...
X
...
X
...
SWE-016
SWE-087
SWE-089
...
Peer Review Metrics
...
# of Non-Conformances identified in each peer review
...
X
...
X
...
X
...
X
...
X
...
SWE-087
SWE-089
...
Peer Review Metrics
...
# of Non-Conformances identified by software assurance during each peer review
...
X
...
X
...
X
...
X
...
X
...
SWE-087
SWE-088
SWE-089
...
Peer Review Metrics
...
Total # of peer review Non-Conformances (Open, Closed)
...
X
...
X
...
X
...
X
...
X
...
SWE-087
SWE-088
SWE-089
...
Peer Review Metrics
...
Preparation time each review participant spent preparing for the review
...
X
...
X
...
X
...
X
...
X
...
SWE-088
SWE-089
...
Peer Review Metrics
...
Time required to close review Non-Conformances
...
X
...
X
...
X
...
X
...
X
...
SWE-087
SWE-088
SWE-089
...
Peer Review Metrics
...
# of peer review participants vs. total # invited
...
X
...
X
...
X
...
X
...
X
...
SWE-088
SWE-089
...
Peer Review Metrics
...
# of peer review Non-Conformances per work product vs. # of peer reviewers
...
X
...
X
...
X
...
X
...
X
...
SWE-088
SWE-089
...
Peer Review Audit Metrics
...
# of audit Non-Conformances per peer review audit
...
X
...
X
...
X
...
X
...
X
...
SWE-088
...
Peer Review Audit Metrics
...
# of Peer Review Audits planned vs. # of Peer Review Audits performed
...
X
...
X
...
X
...
X
...
X
...
SWE-016
SWE-087
SWE-088
...
Peer Review Audit Metrics
...
Trends on non-conformances from audits (Open, Closed, Life cycle Phase)
...
X
...
X
...
X
...
X
...
X
...
SWE-088
SWE-089
...
Peer Review Audit Metrics
...
Time required to close peer review audit Non-Conformances
...
X
...
X
...
X
...
X
...
X
...
SWE-088
SWE-089
...
Peer Review Audit Metrics
...
Preparation time each audit participant spent preparing for audit
...
X
...
X
...
X
...
X
...
X
...
SWE-088
SWE-089
...
Problem/Change Report Status Metrics
...
Total # of Non-Conformances over time (Open, Closed, # of days Open, and Severity of Open)
# of Non-Conformances in current reporting period (Open, Closed, Severity)
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-062
SWE-065c
SWE-065d
SWE-068
SWE-202
SWE-203
SWE-204
...
Problem/Change Report Status Metrics
...
# of safety-related Non-Conformances
...
X
...
X
...
X
...
X
...
X
...
SWE-203
SWE-068
SWE-071
...
Problem/Change Report Status Metrics
...
Trend of Open vs. Closed Non-Conformances over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-053
SWE-054
SWE-065
...
Problem/Change Report Status Metrics
...
Trend of change status over time (# of changes approved, # in implementation, # in test, # closed)
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-018
SWE-053
SWE-080
...
Problem/Change Report Status Metrics
...
# of Non-Conformances identified in embedded COTS, GOT, MOTS, OSS, or reused components in ground or flight software vs. # of Non-Conformances closed
...
X
...
X
...
X
...
SWE-136
SWE-202
SWE-203
SWE-211
...
Problem/Change Report Status Metrics
...
# of Non-Conformances identified in source code products used (Open, Closed)
...
X
...
X
...
X
...
SWE-202
SWE-203
...
Problem/Change Report Status Metrics
...
# of software Non-Conformances at each Severity level for each software configuration item (Open, Closed)
Bold type indicates a required item
...
...
...
...
X
...
X
...
X
...
SWE-202
...
Problem/Change Report Status Metrics
...
# of Closed action items vs. # of Open action items
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-062 SWE-62c
SWE-065d
...
Problem/Change Report Status Metrics
...
# of Root Cause Analyses performed;
# of Non-Conformances identified by each root cause analysis
...
X
...
X
...
X
...
X
...
SWE-204
...
SA Corrective Action (CA) metrics (Issues, Risks)
...
# of Corrective Actions (CAs) raised by SA vs. total #
Attributes (Type, Severity, # of days Open, Life cycle Phase Found)
State (Open, In work, Closed)
Trends of CA Open vs. Closures over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-024
SWE-204
SWE-054
...
SA Corrective Action (CA) metrics (Issues, Risks)
...
Trend the # of inconsistencies or corrective actions identified, and # closed.
...
X
...
X
...
X
...
X
...
X
...
SWE-054
SWE-024
SWE-204
...
Process Improvement Metrics
...
# of software work product Non-Conformances identified by life cycle phase over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-013
SWE-022
SWE-024
SWE-039
SWE-051
SWE-054
SWE-057
SWE-058
SWE-062
SWE-065b
SWE-065c
SWE-065d
SWE-068
SWE-071
SWE-075
SWE-079
SWE-084
SWE-086
SWE-087
SWE-125
SWE-134
SWE-139
SWE-146
SWE-157
SWE-159
SWE-184
SWE-185
SWE-187
SWE-191
SWE-194
SWE-201
SWE-204
SWE-205
...
Process Improvement Metrics
...
# of software process Non-Conformances by life cycle phase over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-032
SWE-039
SWE-061
SWE-077
SWE-080
SWE-082
SWE-085
SWE-086
SWE-088
SWE-139
SWE-195
SWE-204
...
Process Improvement Metrics
...
Identify the specific requirements in NASA-STD-8739.8 that are being tailored by the projects (*organizational metric)
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-121
SWE-125
SWE-013
SWE-176
...
Process Improvement Metrics
...
# of projects tailoring each requirement (*organizational measure)
% of requirements tailored per project (*organizational measure)
...
X
...
X
...
X
...
X
...
SWE-125
SWE-013
SWE-121
...
Process Improvement Metrics
...
% of Total Source Code for each Software Classification (*organizational measure)
...
X
...
X
...
X
...
SWE-020
SWE-176
SWE-087
...
Cost/ Effort Metrics
...
Planned SA resource allocation vs. actual SA resource allocation
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-015
SWE-174
SWE-151
...
Cost/ Effort Metrics
...
Comparison of initial SA cost estimates vs. final cost (capturing assumptions and differences)
...
X
...
X
...
SWE-174
SWE-015
SWE-151
...
Cost/ Effort Metrics
...
Trend SA cost estimates throughout life cycle
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-174
...
Training Metrics
...
% of required training completed for each of the project SA personnel
...
X
...
X
...
X
...
X
...
SWE-017
...
Training Metrics
...
% of project personnel that have completed project specific training against the planned training schedule
...
X
...
X
...
X
...
X
...
X
...
SWE-017
...
Compliance Audit Metrics
...
# of Compliance Audits planned vs. # of Compliance Audits performed
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-024
SWE-039
SWE-139
SWE-016
SWE-032
SWE-077
SWE-195
SWE-082
SWE-084
SWE-085
SWE-086
SWE-088
SWE-079 SWE-201
...
Compliance Audit Metrics
# of Open vs. Closed Audit Non-Conformances over time
# of Non-Conformances per audit (including findings from process and compliance audits, process maturity)
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-022
SWE-024
SWE-039
SWE-139
SWE-016
SWE-032
SWE-077
SWE-079
SWE-195
SWE-082
SWE-084
SWE-085
SWE-086
SWE-088
SWE-201
...
Compliance Audit Metrics
...
# of Non-Conformances identified in plans (e.g., SMPs, SDPs, CM Plans, SA Plans, Safety Plans, Test Plans)
...
X
...
X
...
X
...
X
...
X
...
SWE-024
SWE-013
SWE-075
SWE-079
SWE-139
SWE-071
...
Compliance Audit Metrics
...
# of Non-Conformances identified in the software Configuration Management Plan
Trends of # Open vs. # Closed over time
...
X
...
X
...
X
...
X
...
X
...
SWE-079
...
Compliance Audit Metrics
...
# of Configuration Management Audits conducted by the project – Planned vs. Actual
...
X
...
X
...
X
...
X
...
X
...
SWE-082
SWE-077
SWE-084
...
Compliance Audit Metrics
...
# of Non-Conformances per audit (including findings from process and compliance audits, process maturity)
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-024
SWE-039
SWE-139
SWE-016
SWE-032
SWE-077
SWE-195
SWE-082
SWE-084
SWE-085
SWE-086
SWE-088
SWE-079
...
Compliance Audit Metrics
...
# of process Non-Conformances (e.g., activities not performed) identified by SA vs. # accepted by the project
Trends of # Open vs. # Closed over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-016
SWE-039
SWE-032
SWE-077
SWE-195
SWE-082
SWE-084
SWE-085
SWE-086
SWE-088
...
Compliance Audit Metrics
...
# of Non-Conformances found in flight code, ground code, tools, and COTs products used (Open vs. Closed).
...
X
...
X
...
X
...
X
...
SWE-136
...
Compliance Audit Metrics
...
# of open non-compliances vs. # of closed non-compliances found in security scans or coding standard compliance audits.
...
X
...
X
...
X
...
X
...
SWE-63
...
Project Acceptance Metrics
...
# of Non-Conformances (activities not being performed)
# of Non-Conformances accepted by project
# of Non-Conformances (Open, Closed, Total)
Trends of Open vs, Closed Non-Conformances over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-087
SWE-201
SWE-039
SWE-139
...
Progress Tracking Metrics
...
Deviations of actual schedule progress vs. planned schedule progress above defined threshold
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-016
SWE-018
SWE-046
...
Progress Tracking Metrics
...
# of Software Requirements (e.g. Project, Application, Subsystem, System, etc.)
...
X
...
X
...
X
...
X
...
X
...
SWE-050
SWE-051
SWE-052
SWE-065b
SWE-066
SWE-194
SWE-027
...
Progress Tracking Metrics
...
# of Software Requirements that do not trace to a parent requirement
...
X
...
X
...
X
...
SWE-033
SWE-050
SWE-051
...
Progress Tracking Metrics
...
# of architectural issues identified vs. number closed
...
X
...
SWE-057
SWE-058
SWE-143
...
Progress Tracking Metrics
...
# of planned unit test cases vs. # of actual unit test cases completed
...
X
...
SWE-062
SWE-186
...
Progress Tracking Metrics
...
Total # of tests completed vs. # of test results evaluated and signed off
...
X
...
X
...
SWE-066
SWE-068
SWE-065d
SWE-159
...
Progress Tracking Metrics
...
# of Safety-Critical tests executed vs. # of Safety-Critical tests witnessed by SA
...
X
...
X
...
X
...
SWE-066
SWE-068
SWE-065d
SWE-159
SWE-062
SWE-186
...
Progress Tracking Metrics
...
# of software components (e.g. programs, modules, routines, functions, etc.) planned vs. # actually released in each build
...
X
...
X
...
SWE-194
SWE-077
SWE-073
SWE-036
...
Progress Tracking Metrics
...
# of Non-Conformances from reviews (Open vs. Closed; # of days Open)
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-134
SWE-037
SWE-039
SWE-087
SWE-088
SWE-089
SWE-143
...
Progress Tracking Metrics
...
# of Software Requirements being met via satisfactory testing vs. total # of Software Requirements
...
X
...
X
...
X
...
SWE-065d
SWE-066
SWE-192
SWE-071
...
Progress Tracking Metrics
...
# of Software Requirements without associated test cases
...
X
...
X
...
X
...
SWE-066
SWE-065b
SWE-071
...
Progress Tracking Metrics
...
# of design issues found vs. # of design issues resolved
...
X
...
X
...
SWE-058
...
Progress Tracking Metrics
...
# of planned units for implementation vs. # of units implemented and unit tested.
...
X
...
X
...
X
...
SWE-060
...
Risk Management Metrics
...
# of Risks identified in each life cycle phase (Open, Closed)
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-086
SWE-039
SWE-179
SWE-154
SWE-156
SWE-190
...
Risk Management Metrics
...
# of Risks by Severity (e.g., red, yellow, green) over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-032
SWE-033
SWE-039
SWE-086
SWE-154
SWE-156
SWE-179
SWE-190
SWE-191
...
Risk Management Metrics
...
# of Risks with mitigation plans vs. total # of Risks
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-032
SWE-033
SWE-039
SWE-086
SWE-154
SWE-156
SWE-179
SWE-190
SWE-191
...
Risk Management Metrics
...
# of Risks trending up over time
# of Risks trending down over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-032
SWE-033
SWE-039
SWE-086
SWE-154
SWE-156
SWE-179
SWE-190
SWE-191
...
Cybersecurity Risk Metrics
...
X
...
X
...
X
...
X
...
SWE-154
SWE-156
...
Cybersecurity Risk Metrics
...
·of Cybersecurity Risks with Mitigations vs. # of Cybersecurity Risks identified
...
X
...
X
...
X
...
X
...
SWE-154
SWE-156
SWE-159
...
Traceability Metrics
...
% of traceability completed in each area: System Level requirements to Software requirements; Software Requirements to Design; Design to Code; Software Requirements to Test Procedures
...
X
...
X
...
X
...
X
...
SWE-052
...
Traceability Metrics
...
% of traceability completed for all hazards to software requirements and test procedures
...
X
...
X
...
X
...
X
...
SWE-052
...
Traceability Metrics
...
Defect trends for trace quality (# of circular traces, orphans, widows, etc.)
...
X
...
SWE-051
SWE-052
...
Requirements Metrics
...
# of detailed software requirements vs. # of estimated SLOC to be developed by the project
...
X
...
X
...
X
...
SWE-050
SWE-051
SWE-151
SWE-174
...
Requirements Metrics
...
# of incorrect, missing and incomplete requirements (i.e., # of requirements issues) vs. # of requirements issues resolved
...
X
...
X
...
SWE-051
SWE-053
SWE-054
...
Requirements Metrics
...
Software Requirements Volatility (# of requirements added, deleted, modified, # of TBDs over time)
...
...
X
...
X
...
X
...
X
...
...
SWE-200
SWE-053
...
Requirements Metrics
...
# of TBD/TBC/TBR requirements trended over time
...
...
...
X
...
X
...
X
...
X
...
SWE-066
...
Safety Metrics
...
# of safety-related requirement issues (Open, Closed) over time
...
X
...
X
...
X
...
X
...
X
...
SWE-039
SWE-139
SWE-205
SWE-023
SWE-134
SWE-184
SWE-052
SWE-051
SWE-058
SWE-065b
SWE-066
SWE-071
SWE-192
SWE-080
SWE-087
...
Safety Metrics
...
# of safety-related non-conformances identified by life cycle phase (over time, Open vs. Closed, # of days)
...
X
...
X
...
X
...
X
...
X
...
SWE-013
SWE-039
SWE-139
SWE-143
SWE-121
SWE-184
SWE-023
SWE-134
SWE-052
SWE-051
SWE-057
SWE-058
SWE-135
SWE-062
SWE-065a
SWE-065b
SWE-065c
SWE-065d
SWE-066
SWE-068
SWE-071
SWE-191
SWE-080
SWE-081
SWE-087
SWE-205
...
Reuse Metrics
...
# of products submitted for reuse;
# of developed products submitted for reuse vs. total # of developed products
...
X
...
SWE-147
SWE-148
...
Reuse Metrics
...
# of developed products entered in NASA Internal Sharing & Reuse System vs. total # of developed products
...
X
...
SWE-147
SWE-148
...
Reuse Metrics
...
# of products submitted for reuse vs. # of products entered into NASA Internal Sharing & Reuse Systems
...
X
...
SWE-147
SWE-148
...
Cybersecurity Metrics
...
# of Cybersecurity vulnerabilities and weaknesses identified
# of Cybersecurity vulnerabilities and weaknesses (Open, Closed, Severity)
Trending of Open vs. Closed over time
...
X
...
X
...
X
...
X
...
X
...
X
...
SWE-159
SWE-135
SWE-063
...
Cybersecurity Metrics
...
# and type of vulnerabilities and weaknesses identified by the project
...
X
...
X
...
X
...
X
...
X
...
SWE-135
SWE-063
...
Cybersecurity Metrics
...
# of Cybersecurity vulnerabilities and weaknesses identified by life cycle phase
...
X
...
X
...
X
...
X
...
X
...
SWE-159
SWE-135
SWE-063
...
Cybersecurity Metrics
...
# of Cybersecurity vulnerabilities and weaknesses identified vs. # resolved during Implementation
...
X
...
X
...
X
...
SWE-159
SWE-135
SWE-063
...
Cybersecurity Metrics
...
# of requirements specified relating to detection of adversarial actions vs. # of requirements related to detection of adversarial actions actually implemented
...
X
...
X
...
X
...
SWE-210
...
Cybersecurity Metrics
...
# of Non-Conformances identified in Cybersecurity coding standard compliance (Open, Closed)
...
X
...
X
...
X
...
SWE-063
SWE-135
SWE-207
...
Test Coverage Metrics
...
Software code/test coverage percentages for all identified safety-critical components (e.g., # of paths tested vs. total # of possible paths)
Note: Metrics in bold type are required by all projects
...
X
...
SWE-066
SWE-190
SWE-189
SWE-219
...
Test Coverage Metrics
...
Test coverage data for all identified safety-critical software components.
...
X
...
SWE-219
...
Test Coverage Metrics
...
% of code that has been executed during testing
...
X
...
SWE-060
...
Static Code Metrics
...
Document the Static Code Analysis tools used with associated Non-Conformances
·of total errors and warnings identified by the tool
# of errors and warnings evaluated vs. # of total errors and warnings identified by the tool
...
X
...
SWE-135
SWE-185
...
Static Code Metrics
...
# of Non-Conformances raised by SA vs. total # of raised Non-Conformances
...
X
...
SWE-135
SWE-185
...
Static Code Metrics
...
# of static code errors and warnings identified as “positives” vs. # of total errors and warnings identified by the tool
Total # of static code analysis "positives" vs. # of "positives" resolved. Trend over time.
# of static code errors and warnings resolved by Severity vs. # of static code errors and warnings identified by Severity by the tool
...
X
...
SWE-135
SWE-185
...
Static Code Metrics
...
# of static code “positives” over time (Open, Closed, Severity)
...
X
...
X
...
SWE-135
SWE-185
...
Static Code Metrics
...
# of Cybersecurity vulnerabilities and weaknesses identified by the tool
...
X
...
X
...
SWE-135
SWE-185
...
Static Code Metrics
...
# of coding standard violations identified (Open, Closed, type of violation, Severity)
...
X
...
SWE-061
SWE-185
...
Static Code Metrics
...
Software cyclomatic complexity # for all identified safety-critical components
...
X
...
X
...
SWE-087
SWE-134
...
Static Code Metrics
...
Trend of # of total errors and warnings identified per SCA Tool, Language, and SLOC size
...
X
SWE-135
...
Static Code Metrics
...
Total # of static code analysis "positives" vs. # of "positives" resolved. Trend over time.
...
X
...
SWE-135
...
Test Procedures Metrics
...
# of Non-Conformances and risks open vs. # of Non-Conformances, risks, identified with test procedures
...
X
...
X
...
SWE-087
SWE-065b
SWE-071
SWE-191
...
Test Procedures Metrics
...
# of hazards with completed test procedures/cases vs. total number of hazards over time
...
X
...
X
...
SWE-065b
SWE-068
SWE-191
...
Test Procedures Metrics
...
# of software requirements with completed test procedures/cases over time
...
X
...
X
...
SWE-065b
SWE-071
SWE-066
...
Test Procedures Metrics
...
# of Non-Conformances identified when the approved, updated requirements are not reflected in test procedures
...
X
...
X
...
SWE-065b
SWE-071
SWE-052
SWE-066
SWE-191
...
Test Procedures Metrics
...
# of Non-Conformances identified while confirming hazard controls are verified through test plans/procedures/cases
...
X
...
X
...
SWE-065b
SWE-071
SWE-066
SWE-068
SWE-191
...
Test Procedures Metrics
...
# of issues and risks/corrective actions open vs. total # of issues and risks/corrective actions identified with test procedures
...
X
...
X
...
X
...
SWE-065b
...
Test Metrics
...
# of tests executed vs. # of tests completed
...
X
...
X
...
X
...
SWE-062
SWE-066
SWE-065d
SWE-068
SWE-159
SWE-190
SWE-192
SWE-055
SWE-080
SWE-191
SWE-194
SWE-211
...
Test Metrics
...
# of Non-Conformances identified during each testing phase (Open, Closed, Severity)
...
X
...
X
...
X
...
SWE-062
SWE-065d
SWE-066
SWE-068
SWE-080
SWE-159
SWE-190
SWE-191
SWE-192
SWE-194
SWE-211
...
Test Metrics
...
·of Requirements tested vs. total # of Requirements
...
X
...
X
...
X
...
SWE-062
SWE-065b
SWE-065d
SWE-066
SWE-080
SWE-191
SWE-192
SWE-194
...
Test Metrics
...
# of Hazards containing software that have been tested vs. total # of Hazards containing software
...
X
...
X
...
X
...
SWE-062
SWE-066
SWE-068
SWE-080
SWE-134
SWE-192
SWE-205
...
Test Metrics
...
# of Non-Conformances identified in models, simulations, and tools over time (Open, Closed, Severity)
...
X
...
X
...
X
...
SWE-070
...
Test Metrics
...
# of Regression test set Non-Conformances/Risks over time (Open, Closed, Severity)
...
X
...
X
...
X
...
SWE-191
...
Test Metrics
...
# of Requirements tested in customer environment vs. # of Requirements
...
X
...
X
...
SWE-055
...
Cybersecurity Metrics During Testing Metrics
...
# of Cybersecurity mitigation implementations identified from the security vulnerabilities and security weaknesses
...
X
...
X
...
X
...
SWE-154
SWE-159
SWE-191
...
Cybersecurity Metrics During Testing Metrics
...
# of Cybersecurity mitigation implementations identified with associated test procedures vs. # of Cybersecurity mitigation implementations identified
...
X
...
X
...
X
...
SWE-154
SWE-159
SWE-191
...
Cybersecurity Metrics During Testing Metrics
...
# of Cybersecurity mitigation tests completed vs. total # of Cybersecurity mitigation tests
...
X
...
X
...
X
...
SWE-159
...
Cybersecurity Metrics During Testing Metrics
...
# of Non-Conformances identified during Cybersecurity mitigation testing (Open, Closed, Severity)
...
X
...
X
...
X
...
SWE-159
...
Cybersecurity Metrics During Testing Metrics
...
Trends of Cybersecurity Non-Conformances over time
...
X
...
X
...
X
...
SWE-159
SWE-063
SWE-135
SWE-201
...
Test Coverage Metrics
...
Software code/test coverage percentages for all identified safety-critical components (e.g., # of paths tested vs. total # of possible paths)
...
...
...
...
X
...
X
...
X
...
SWE-066
SWE-190
SWE-134
SWE-189
...
Test Coverage Metrics
...
# of tests completed vs. total # of tests
...
X
...
X
...
X
...
SWE-055
SWE-062
SWE-066
SWE-065d
SWE-068
SWE-080
SWE-159
SWE-190
SWE-191
SWE-192
SWE-194
SWE-211
...
Test Coverage Metrics
...
# of detailed software requirements tested to date vs. total # of detailed software requirements
...
X
...
X
...
X
...
SWE-055
SWE-062
SWE-065b
SWE-065d
SWE-066
SWE-071
SWE-080
SWE-191
SWE-192
SWE-194
SWE-159
...
Test Coverage Metrics
...
# of safety-critical requirement verifications vs. total # of safety-critical requirement verifications completed
# of Open issues vs. # of Closed over time
...
X
...
X
...
X
...
SWE-062
SWE-066
SWE-191
SWE-192
SWE-068
...
Test Coverage Metrics
...
# of Source Lines of Code (SLOC) tested vs. total # of SLOC
...
X
...
X
...
X
...
SWE-066
SWE-134
SWE-189
SWE-190
SWE-219
...
Build/Release Content Metrics
...
# of software units planned vs. # actually built
...
X
...
X
...
X
...
X
...
SWE-063
SWE-194
...
Build/Release Content Metrics
...
# of planned software requirements implemented in each build vs. # of actual software requirements implemented in each build
...
X
...
X
...
X
...
SWE-063
SWE-194
...
Build/Release Content Metrics
...
# of Non-Conformances identified in release documentation (Open, Closed)
...
X
...
X
...
X
...
SWE-063
SWE-077
SWE-084
SWE-085
...
Operations/ Maintenance Metrics
...
# of Non-Conformances identified in the software after delivery
...
X
...
SWE-195
...
Other Metrics
...
Measures relating to status and performance as identified in other requirements. (Schedule deviations, closure of corrective actions, product and process audit results, peer review result, etc)
...
X
...
X
...
X
...
X
...
SWE-093
...
Other Metrics
...
# of requirements being met, any TBD/TBC/TBR requirements, or any requirements that are not being met
Performance and functionality measures (Schedule deviations, closure of corrective actions, product and process audit results, peer review results, requirements volatility, # of requirements satisfactorily tested vs. total # of requirements, etc.)
...
X
...
X
...
X
...
X
...
SWE-199
...
Other Metrics
...
# of findings open vs. # of findings identified
...
X
...
X
...
X
...
X
...
X
...
SWE-082
...
Other Metrics
...
Trends of Open vs. Closed Non-Conformances change reports over time.
...
X
...
X
...
X
...
X
...
X
...
SWE-065d
...
IV&V Metrics (Kept by IV&V)
...
# of IV&V Non-Conformances/issues,/risks (Open, Closed, accepted by the project, severity, category of Non-Conformance (e.g., requirements severity, category (requirements, design, code, test, documentation, etc.))
Kept by IV&V team, not SA
...
X
...
X
...
X
...
X
...
X
...
X
SWE-179
...
Coverage Metrics
...
Code coverage data: % of code that has been executed during testing
...
X
...
X
...
X
...
SWE-060
...
Coverage Metrics
...
Test coverage data for all identified safety-critical software components.
...
X
...
X
...
X
...
SWE-219