{alias:SWE-089}
{tabsetup:1. The Requirement|2. Rationale|3. Guidance|4. Small Projects|5. Resources|6. Lessons Learned}

{div3:id=tabs-1}

h1. 1. Requirements

4.3.4 The project shall, for each planned software peer review/inspection, record basic measurements.

h2. {color:#003366}{*}1.1 Notes{*}{color}

The requirement describing the contents of a Software Peer Review/Inspection Report is defined in Chapter 5 of NPR 7150.2.

h2. 1.2 Applicability Across Classes

Class F is labeled with "X (not OTS)". This means that this requirement does not apply to off-the-shelf software for these classes.

Class G is labeled with "P(Center)". This means that an approved Center-defined process which meets a non-empty subset of the full requirement can be used to achieve this requirement.

{applicable:asc=1|ansc=1|bsc=1|bnsc=1|csc=0|cnsc=0|dsc=0|dnsc=0|esc=0|ensc=0|f=*|g=p|h=0}
{div3}
{div3:id=tabs-2}

h1. 2. Rationale

As with other engineering practices, it is important to monitor defects, pass/fail results, and effort. This is necessary to ensure that peer reviews/inspections are being used in an appropriate way as part of the overall software development life cycle, and to be able to improve the process itself over time. Moreover, key measurements are required to interpret inspection results correctly -- for example, if very little effort is expended on an inspection or key phases (such as individual preparation) are skipped altogether, it is very unlikely that the inspection will have found a majority of the existing defects.
{div3}
{div3:id=tabs-3}

h1. 3. Guidance

The Software Formal Inspection Standard is currently being updated and revised to include lessons that have been learned by practitioners over the last decade.

The creators of the updated Software Formal Inspection Standard suggest several best practices related to the collection and the use of inspection data.

This requirement along with [SWE-119|SWE-119] collects effort, number of participants, defects, number and types of defects found, pass/fail, and identification in order to ensure the effectiveness of the inspection. Where peer reviews/inspections yield less than expected results, some questions to address may include:

* Are peer reviews/inspections being deployed for the appropriate artifacts? As described in the rationale for [SWE-087|SWE-087], this process often is most beneficial when applied to artifacts such as requirements and test plans.

* How are peer reviews/inspections being applied with respect to other verification and validation activities? It may be worth considering whether this process is being applied only after other approaches to quality assurance (e.g., unit testing) that are already finding defects, perhaps less cost-effectively.

* Are peer review/inspection practices being followed appropriately? Tailoring away key parts of the inspection process (e.g., planning or preparation), or undertaking inspections with key expertise missing from the team, will not produce the best results.

As with other forms of software measurement, best practices for ensuring that the collection and analysis of peer review/inspection metrics are done well include:

* There should be clear triggers as to when the metrics are gathered and analyzed (e.g., after every inspection; once per month).

* It should be clear who has been assigned to do this task.

* The units of measure are recorded consistently, e.g., one inspection does not record effort in person-hours and another in calendar-days.

* Measures should be checked for consistency once collected, and for outliers it should be investigated whether the data was entered correctly and the correct definitions were applied.

Best practices related to the collection and analysis of inspection data include:

* The moderator is to be responsible for compiling and reporting the inspection data.

* The project manager explicitly specifies the location and the format of the recorded data.

* Inspections are checked for process compliance using the collected inspection data, for example to verify that:
** Any inspection team consists of at least of three persons.
** Any inspection meeting is limited to approximately two hours, and if the discussion looks likely to extend far longer, the remainder of the meeting is rescheduled for another time when inspectors can be fresh and re-focused.
** The rate of inspection adheres to the recommended or specified rate for different inspection types.

* A set of analyses are performed periodically on the recorded data to monitor progress (i.e., number of inspection planned versus completed) and to understand the costs and benefits of inspection.

* The outcome of the analyses is leveraged to support the continuous improvement of the inspection process.

In an acquisition context, there are several important considerations for assuring proper inspection usage by software provider(s):

* The metrics to be furnished by software provider(s) must be specified in the contract.

* It must be clear and agreed upon ahead of time whether or not software providers can define their own defect taxonomies. If providers may use their own taxonomy, request the software providers furnish the definition or the data dictionary of the taxonomy. It is also important (especially when the provider team contains subcontractors) to ensure that consistent definitions are used for: defect types; defect severity levels; effort reporting (how comprehensive or restrictive are the activities that are part of the actual inspection).

Additional guidance regarding software peer review/inspection measures can be found in the guidebook section for [SWE-119|SWE-119].


{note}Consult Center Process Asset Libraries (PALs) for Center-specific guidance and resources, such as templates, related to peer reviews and inspections. {note}
{div3}
{div3:id=tabs-4}

h1. 4. Small Projects

Projects with small budgets or a limited number of personnel need not use heavy-weight data collection logistics.

Given the amount of data typically collected, lightweight tools such as Excel sheets or small databases (e.g., implemented in MS Access) are usually sufficient to store and analyze the inspections performed on a project.


{div3}
{div3:id=tabs-5}

h1. 5. Resources

# NASA Technical Standard, ["Software Formal Inspections Standard" |https://standards.nasa.gov/documents/detail/3315679], NASA-STD-2202-93, 1993.
# John C. Kelly, Joseph S. Sherif, Jonathan Hops, "An analysis of defect densities found during software inspections", Journal of Systems and Software, Volume 17, Issue 2, February 1992, Pages 111-117.

{toolstable}


{div3}
{div3:id=tabs-6}

h2. 6. Lessons Learned

Over the course of hundreds of inspections and analysis of their results, JPL has identified key lessons learned which lead to more effective inspections, including:

* Statistics on the number of defects, the types of defects, and the time expended by engineers on the inspections are kept. ^2^