1. Requirements
6.1.2 Where approved, the requesting Center or project shall document the approved alternate requirement in the procedure controlling the development, acquisition, and/ or deployment of the affected software.
1.1 Notes
NPR 7150.2, NASA Software Engineering Requirements, does not include any notes for this requirement.
1.2 Applicability Across Classes
This requirement applies to all classes and safety criticalities.
...
f | 1 |
---|---|
g | 1 |
h | 1 |
asc | 1 |
ansc | 1 |
bnsc | 1 |
csc | 1 |
bsc | 1 |
esc | 1 |
cnsc | 1 |
dsc | 1 |
dnsc | 1 |
ensc | 1 |
Div | ||
---|---|---|
| ||
2. RationaleThe Center is required to record the alternate requirements obtained through the use of SWE-120 in Center or program/project documentation that controls the development, acquisition, and deployment of the affected software. Publication of the approved alternate requirements helps assure that all affected software engineers are informed of the approved changes. This action will assure the proper implementation of the alternate requirement throughout the various stages of the software life cycle. (See SWE-019 for information on the life cycle process.) The inclusion of these changes in a configuration managed system for the Center or program/project will inform current and future software product developers and project managers of the correct set of requirements and procedures. |
Div | ||
---|---|---|
| ||
3. GuidanceProject personnel record the appropriate information on any requirements changes resulting from the approval of a request made under SWE-120 in the project-specific software requirements documents. This information is placed in the project plan, the software management plan, and the software requirements specification. The Center's compliance matrix to NPR 7150.2 will also include the results of the approval by the Headquarters' Office of the Chief Engineer (OCE). The software team lead will include any updates in the compliance matrix that reflect approved alternate requirements. The software team lead also communicates this information to affected software Technical Authorities (TAs). (See SWE-125 and SWE-128 for information on the content and handling of a compliance matrix.) When approval is granted for an action from SWE-120, the program/project also includes the results of the request and the rationale for the request, along with any approved alterations to the initial request, in the baselined program/project documentation. Typically, Center changes are reflected in the Center's local implementation of the flowdown of NPR 7150.2, e.g., Center Directives, Center Procedural Requirements covering software engineering, and software assurance plans. The Center-level procedure typically is stored in the Center's central documentation repository. As the alternate requirements generally affect processes, related process assets are updated in the process asset library for future use by software development teams within scope of the generic waiver. |
Div | ||
---|---|---|
| ||
4. Small ProjectsSmall projects may lack the resources and schedule to individually apply for waiver relief from specific sets of NPR 7150.2 requirements. Centers can request a generic waiver (waived in accordance with SWE-120 and documented under SWE-121) that will cover multiple small projects. |
...
id | tabs-5 |
---|
5. Resources
...
toolstable |
---|
...
id | tabs-6 |
---|
6. Lessons Learned
A documented lesson from the NASA Lessons Learned database notes the following:
...