1. Requirements
6.3.4 Centers and projects shall fully comply with the "shall" statements in this NPR that are marked with an "X" in Appendix D consistent with their software classification.
1.1 Notes
If the requirement is marked with a "SO" in appendix D, the project is required to meet the requirement to the extent necessary to satisfy the safety critical aspects of the software.
1.2 Applicability Across Classes
This requirement applies to all classes and safety criticalities.
applicable
f
1
g
1
h
1
ansc
1
asc
1
bnsc
1
csc
1
bsc
1
esc
1
cnsc
1
dnsc
1
dsc
1
ensc
1
Div
id
tabs-2
2. Rationale
Earlier versions of NPR 7150.2, NASA Software Engineering Requirements, assumed that readers would accept requirements marked by an "X" in Appendix D as required activities. Experience with the baseline version of this NPR, i.e., NPR 7150.2, showed that this assumption was not universally confirmed.
Panel
NPR 7150.2 was written to include the explicit statement in the requirement that full compliance with the requirement is necessary for those entries assigned an "X" in Appendix D.
The purpose of the Requirements Mapping Matrix in NPR 7150.2 is to essentially pre-tailor out requirements for less critical software systems, e.g., while Class A software has 111 invoked requirements for projects, Class H has only 16. The purpose of the "X" label is to clarify the intent of NPR 7150.2 and to preclude any alternate interpretation of invoked requirements.
Div
id
tabs-3
3. Guidance
This requirement affirms that designated Center and project personnel are to satisfy all invoked requirements of this NPR. The note further affirms that at least the safety aspects of an NPR requirement are to be satisfied if the requirement is simply labeled in NPR 7150.2, Appendix D, as "safety only" (SO).
This requirement makes a positive statement that the invoked requirement is to be fulfilled by the SWE's responsible party (indicated by the 4th column in the same Appendix D, Requirements Mapping Matrix).
Note
Inherently, it affirms that fulfillment of requirements marked with an "X" is the rule for specific NASA software classifications.
Deviations, waivers, and tailoring of the requirements of NPR 7150.2 are to follow the approved processes for requirements management. (See SWE-120 and SWE-140.)
Div
id
tabs-4
4. Small Projects
No additional guidance is available for small projects. The community of practice is encouraged to submit guidance candidates for this paragraph.
Div
id
tabs-5
5. Resources
refstable
toolstable
Div
id
tabs-6
6. Lessons Learned
There are currently no Lessons Learned identified for this requirement.