Tabsetup
1. The Requirement
1. The Requirement
12. Rationale
23. Guidance
34. Small Projects
45. Resources
56. Lessons Learned


Div
idtabs-1

1. Requirements

3.5.3 The project shall implement software operations, maintenance, and retirement activities as defined in the respective plans.

1.1 Notes

NPR 7150.2, NASA Software Engineering Requirements, does not include any notes for this requirement.

1.2 Applicability Across Classes

Class G is labeled as "P (Center)." This means that an approved Center-defined process which meets a non-empty subset of the full requirement can be used to achieve this requirement.


applicable
f1
gp
h0
ansc1
asc1
bnsc1
csc1
bsc1
esc1
cnsc1
dnsc0
dsc1
ensc0



Div
idtabs-2

2. Rationale


Panel

While NPR 7150.2 requirement SWE-075 requires a software team to plan for operations, maintenance, and retirement, this SWE (076) requires that the team implement the planning described in that Software Maintenance Plan.


The maintenance plan describes the activities and processes that the project team will carry out during the operations, maintenance, and retirement phases of the software life cycle. Those plans are created to guide the work and increase the possibility of meeting project expectations and long-term goals.

The maintenance plan takes over where the Software Development/Management Plan (SDP/SMP) left off for the initial software development. Project stakeholders review and agree to the plan before the operations, maintenance, and retirement phases begin and the project is held accountable for following the approved plan.


Div
idtabs-3

3. Guidance

The project team baselines the maintenance plan before it is implemented to ensure that the team carrying out the operations, maintenance, and retirement activities executes only the approved plan. Software Assurance personnel are responsible for assuring that these activities are carried out per the baselined maintenance plan.

There are fewer reasons for the maintenance plan to require revision than plans used for the earlier life-cycle phases, but keep the following in mind as a non-exhaustive list of events that could cause the maintenance plan to require updating:

  • Changes in resource levels, availability (e.g., tools, facilities, personnel).
  • In response to new or revised risks.
  • Budget changes.
  • Changes in stakeholders/stakeholder needs.
  • Changes in processes used for operations, maintenance, retirement (e.g, reporting processes, review processes, record keeping processes).

As with other project documents, updates to the Software Maintenance Plan are reviewed and approved before being implemented.


Note

Consult Center Process Asset Libraries (PALs) for Center-specific guidance related to implementing operations, maintenance, and retirement.


For NPR 7120.5 projects, this Handbook provides the recommended maturity of the Software Maintenance Plan at major milestone reviews (see Maturity of Life cycle Products at Milestone Reviews). Additionally, guidance related to operations, maintenance, and retirement planning may be found in the following related requirements in this Handbook:


SWE-013

Software Plans (Execute Planning)

SWE-074

Document Maintenance Plan

SWE-075

Plan Operations, Maintenance, Retirement

SWE-105

Software Maintenance Plan



Div
idtabs-4

4. Small Projects

No additional guidance is available for small projects. The community of practice is encouraged to submit guidance candidates for this paragraph.


Div
idtabs-5

5. Resources


refstable



toolstable


Div
idtabs-6

6. Lessons Learned

A documented lesson from the NASA Lessons Learned database notes the following:

ADEOS-II NASA Ground Network (NGN) Development and Early Operations – Central/Standard Autonomous File Server (CSAFS/SAFS) Lessons Learned (Tools for Maintenance.) Lesson Number 1346:  Lesson Learned No. 3 states: "Install, operate and maintain the COTS (Commercial Off-the-Shelf) field and lab components. The following lessons were learned in the installation and operation phase of the SAFS/CSAFS ((Standard/Central Standards Autonomous File Server)) development.

  • "Personally perform on-site installations whenever possible.
  • "Have support/maintenance contracts for hardware and software through development, deployment, and first year of operation.
  • "Create visual representations of system interactions where possible.
  • "Obtain feedback from end users.
  • "Maintain the prototype system after deployment.
  • "Select COTS COTS products with the ability to do internal logging."