bannerd

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Describe what conditions determine if the activity needs to be repeated, such as re-planning after a change in requirements or schedule constraints. 

  • How much of the activity needs to be repeated
  • Frequency of repetition
  • Design is always done once. It should be peer reviewed and analyzed by Software Assurance. 
  • Design may be reviewed and re-analyzed as often as there are significant changes in architecture or requirements. For example:  
    • Technology changes to the architecture requires changes to the design
    • Customer changes to requirements require changes to the design

1.6 Center Resources From SPAN

Add links to SPAN activity pages that are appropriate for this activity. Use links from the Activity section of the front page. 

SPAN

 All  of the links to SPAN activities are provided. Delete the ones that do not apply

Several Centers Process Asset Libraries have materials related to this activity. Related Processes, templates, and other resources may be found in the following Activities in SPAN (available to NASA only). 

Tabsetup
01. Introduction
12. Software Engineering
23. Software Assurance
List of some of the inputs from other activities

Documents that are necessary for

the activity

Design to begin

Examples

1.2 Predecessor Activities

List of some of the other activities that must be started (not necessarily completed) so that this activity may begin. 

Examples: 

Predecessor Activities are performed before Design. These activities produce the work products that will be reviewed. 

1.3 Outputs

note


Div
idtabs-1

1. Introduction

Note

Typically starts with a quote from the NPR that helps define the activity. Additional descriptive material is meant to help define the activity but not be so detailed that it pulls in all of the guidance from the SWEs in the activity. 


Panel
borderColorblue
titleNPR 7150.2B para 4.3.1

Include Page
2D-Para 4.3.1
2D-Para 4.3.1
Software peer reviews and inspections are the in-process technical examination of work products by peers to find and eliminate defects early in the life cycle. Software peer reviews and inspections are performed following defined procedures covering the preparation for the review, the review itself is conducted, results are recorded, results are reported, and completion criteria is certified. When planning the composition of a software peer review or inspection team, consider including software testing, system testing, software assurance, software safety, software cybersecurity, and software IV&V personnel.

Panel
borderColorblack
borderWidth2
titleInputs, Outputs, and Predecessor Related Activities

Activity graphical representation of Inputs, Outputs, Predecessor and Successor Activities as appropriate. Not meant to be exhaustive, but representative of a typical project. 

1.1 Inputs

Note
Note

List of some of the outputs or work products of the activity. These are typically used as inputs by the downstream activity. In some cases there is a supporting SWE associated with the work product. 

Output Work ProductUsed by Downstream Activity
  • Implementation and Unit Testing
  • Preliminary at Preliminary Design Review
  • Baselined at Critical Design Review
  • Updated at Test Readiness Review
  • Implementation and Unit Testing
  • Preliminary at Preliminary Design Review
  • Baselined at Critical Design Review
  • Updated at Test Readiness Review
  • Implementation and Unit Testing
  • Baselined at Operational Readiness Review

1.4 Successor Activities

Note

Links to Activities which might be started or supported by this activity. 

  • Implementation and Unit Testing - Implements the Design into one or more code modules. 
  • Preliminary Design Review
  • Critical Design Review
  • Test Readiness Review
  • Operational Readiness Review

1.5 Activity Repetition

Note
Note
ActivityDescription

Design

Assets for use during product design
This section contains the links to SWE pages that form the heart of the activity.  For each SWE, the related tasks from tab 4 are listed. 

SWE-058 - Detailed Design with new tab 4

Div
idtabs-2

2. Software Engineering

Note

This tab contains the links to pages in the SWEHB that are at the heart of the activity. 

2.1 SWEs

Note
Expand
titleSWE-058 Tasking and Work Product Details

Link to SWE-058 - Copy of SWE-058 - Detailed Design with new tab 4

Class Applicability: A B C

SWE-058 Requirement

Excerpt Include
Copy of SWE-058 - Detailed Design with new tab 4
Copy of SWE-058 - Detailed Design with new tab 4
nopaneltrue

Include Page
SWE-058-ETask
SWE-058-ETask

Include Page
SWE-058-EWP
SWE-058-EWP

2.2 Topics and other Supporting Materials

NoteThis section is for SWEHB pages, other than SWEs, that directly support the activity. This section contains Topics, PATs, and other relevant pages. 

2.2.1 Topics

Expand
titleSWE-058 Topics

Include Page
SWE-058-TopicsETopics
SWE-058-TopicsETopics

2.2.2 Supporting Materials

Expand
titleSWE-058 Supporting Materials

Include Page
SWE-058-SupportESupport
SWE-058-SupportESupport

2.3 Other Associated SWEs, Topics, etc.

note

Includes other SWEHB pages that are indirectly associated with the activity. May include SWEs, Topics, document definition pages, PATs, etc. They may have been mentioned in the guidance of another page. This section may be removed if there is no content for it. 


PAT-023 - Preparing for a SARB Checklist

excerpt-

Div
idtabs-3

3. Software Assurance

Software Assurance is integral to the performance of all Software Development activities. It includes Process Monitoring as well as Process Analysis. 

  • Process Monitoring - addresses the question, "Is the development team following their processes and producing the expected work products?"
  • Process Analysis - addresses the question, "Are there better ways of performing the processes that would result in the early discovery of defects?"

3.1 Software Assurance Tasks from SWEs

Software Assurance Tasks are included in tab 7 of the SWEs in this activity. 

3.1.1

SWE-058 - Detailed Design with new tab 4

Expand
titleSWE-058 SA Tasking and Work Product Details

Link to SWE-058 Copy of SWE-058 - Detailed Design with new tab 4

SWE-058 Requirement

Excerpt Include
Copy of SWE-058 - Detailed Design with new tab 4
Copy of SWE-058 - Detailed Design with new tab 4
nopaneltrue

Tasking From NASA-STD-8739.8B

Include Page
SWE-058 - SA Task1
SWE-058 - SA Task1

Include Page
SWE-058 - SA Task2
SWE-058 - SA Task2

Include Page
SWE-058 - SA Task3
SWE-058 - SA Task3

Include Page
SWE-058 - SA Task4
SWE-058 - SA Task4

Include Page
SWE-058 - SA Task5
SWE-058 - SA Task5

Software Assurance

SA Work Products

  1.  Software Design Analysis
  2.  Results of software assurance design analysis, including assessments in Tasks 1, 2, and 3. 
  3.  List of any identified design risks and issues.
  • Metrics
    1. # of architectural issues identified vs. number closed.
    2. # of design issues found versus the number of design issues resolved.
    3. # of safety-related requirement issues (Open, Closed) over time.
    4. # of safety-related non-conformances identified by life cycle phase over time.
    5. # of software work product Non-Conformances identified by life cycle phase over time

Include Page
SWE-058-SAWP
SWE-058-SAWP

3.2 Topics and Other Supporting Materials

3.2.1 Topics

  • Topic 8.16 - 8.55 - Software Design Analysis
    • Excerpt Include
      SWEHBVD:8.55 - Software Design Analysis
      SWEHBVD:8.55 - Software Design Analysis
      nopaneltrue
      SA Tasks for SWEs
Expand
titleSA Tasking from Topic 8.16 - Software Design Analysis

3.2.2 Process Asset Templates

PAT-021 - SADESIGN Checklist
Excerpt Include
PAT-021 - SADESIGN ChecklistPAT-021 - SADESIGN Checklist
nopaneltrue
Include Page

PAT-023 - Preparing for a SARB ChecklistPAT-023 - Preparing for a SARB ChecklistnopaneltruePAT-031 - Critical Design Analysis Checklist Excerpt IncludePAT-031 - Critical Design Analysis ChecklistPAT-031 - Critical Design Analysis ChecklistnopaneltruePAT-008 - Safety Considerations for Design Peer Reviews Checklist Excerpt IncludePAT-008 - Safety Considerations for Design Peer Reviews ChecklistPAT-008 - Safety Considerations for Design Peer Reviews ChecklistnopaneltruePAT-020 - Examples of Interface Problems

Design Analysis Process Asset Templates
Design Analysis Process Asset Templates

Excerpt IncludePAT-020 - Examples of Interface ProblemsPAT-020 - Examples of Interface Problemsnopaneltrue

3.3 Other Associated SWEs, Topics, etc.

NoteIncludes other SWEHB pages that are indirectly associated with the activity. May include SWEs, Topics, document definition pages, PATs, etc. They may have been mentioned in the guidance of another page. This section may be removed if there is no content for it.