bannerd

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Tabsetup
01. Introduction
12. Defining the Activity
Div
idtabs-1

1. Introduction

Note

Typically starts with a definition of the activity. Additional descriptive material is meant to help define the activity but not be so detailed that it pulls in all of the guidance from the SWEs in the activity. 

Planning of Software Assurance activities in a Software Development Project are done in a collaborative fashion along with the Software Development team. As a part of that collaboration, several Software Assurance tasks most be startedIt includes cost estimates and schedules


Panel
borderColorblack
borderWidth2
titleInputs, Outputs, and Predecessor Activities

Activity graphical representation of Inputs, Outputs, Predecessor and Successor Activities as appropriate. Not meant to be exhaustive, but representative of a typical project. 

 1.1 Inputs

Note

List of some of the inputs from other activities that are necessary for the activity to begin. 

Examples: 

  • Planning - Peer Reviews are planned activities. They appear in the plans and schedules for the project
  • Requirements - These are the things that are Peer Reviewed
  • Architecture Items - These are the things that are Peer Reviewed
  • Design items - These are the things that are Peer Reviewed
  • Test Plans and Procedures - These are the things that are Peer Reviewed

1.2 Predecessor Activities

Note

List of some of the other activities that must be started (not necessarily completed) so that this activity may begin. 

Examples: 

Predecessor Activities are performed before Peer Reviews. These activities produce the work products that will be reviewed. 

  • Life Cycle Planning - plans, schedules, estimates, etc.
  • Software Architecture 
  • Software Design
  • Software Testing - plans and procedures

1.3 Outputs

Note

List of some of the outputs or work products of the activity. These are typically used as inputs by the downstream activity. In some cases there is a supporting SWE associated with the work product. 

Examples: 

The activities that initiated the Peer Review, receive the findings from Peer Reviews, Those activities then use those findings to to fix defects and implement improvements uncovered in the reviews. 

Output Work ProductUsed by Downstream Activity
  • SA Plan
  • SA Auditing
  • SA SW Requirements Analysis
  • SA SW Source Code Analysis
  • SA SW Testing Analysis
  • SA Reporting
  • SA Design Analysis
  • SA Safety and Hazard Anaysis
  • Peer Review Findings
  • Life Cycle Planning
  • Software Architecture 
  • Software Design
  • Software Testing
  • Configuration Management
  • Coding

1.4 Successor Activities

Note

Links to Activities which might be started or supported by this activity. 

  • SA Auditing
  • SA SW Requirements Analysis
  • SA SW Source Code Analysis
  • SA SW Testing Analysis
  • SA Reporting
  • SA Design Analysis
  • SA Safety and Hazard Anaysis

1.5 Activity Repetition

Note

Describe what conditions determine if the activity needs to be repeated, such as re-planning after a change in requirements or schedule constraints. 

  • How much of the activity needs to be repeated
  • Frequency of repetition

This activity is done in the early stages of a Software Project. Other work may be started before the planning is actually completed. 

During the life of the project there may be multiple times when significant changes to things like requirements, budget, schedule, technology, which make re-planning necessary. Re-planning is covers the same areas of the original planning to make sure that all changes are accounted for in the new plans. Re-planning is done as often as necessary to keep the project under control. 

1.6 Center Resources From SPAN

Note

Add links to SPAN activity pages that are appropriate for this activity. Use links from the Activity section of the front page. SPAN

Several Centers Process Asset Libraries have materials related to this activity. Related Processes, templates, and other resources may be found in the following Activities in SPAN (available to NASA only). 


Div
idtabs-2

2. Defining the Activity

Note

This tab contains the links to pages in the SWEHB or excerpts from the NASA-STD-8739.8B that are at the heart of the activity. 

2.1 SWEs

Note

This section contains the links to SWE pages that form the heart of the activity. In the case of Software Assurance, copy in the task table from each of the tab 7.1 from appropriate SWEs. 

Link to the SWE goes here

  • Excerpt include for the SWE goes here (Remove Surrounding Panel)
SITE:SWE-034
SWERequirementSA Tasks

SWE-033 - Acquisition vs. Development Assessment

Excerpt Include
SWEHBVD:SWE-033 - Acquisition vs. Development Assessment
SWEHBVD:SWE-033 - Acquisition vs. Development Assessment
nopaneltrue

Include Page
SWE-033 - SA Task1
SWE-033 - SA Task1

Include Page
SWE-033 - SA Task2
SWE-033 - SA Task2

Include Page
SWE-033 - SA Task3
SWE-033 - SA Task3

SWE-013 - Software Plans

Excerpt Include
SWEHBVD:SWE-013 - Software Plans
SWEHBVD:SWE-013 - Software Plans
nopaneltrue

Include Page
SWE-013 - SA Task1
SWE-013 - SA Task1

Include Page
SWE-013 - SA Task2
SWE-013 - SA Task2

SWE-024 - Plan Tracking

Excerpt Include
SWEHBVD:SWE-024 - Plan Tracking
SWEHBVD:SWE-024 - Plan Tracking
nopaneltrue

Include Page
SWE-024 - SA Task1
SWE-024 - SA Task1

Include Page
SWE-024 - SA Task2
SWE-024 - SA Task2

Include Page
SWE-024 - SA Task3
SWE-024 - SA Task3

SWE-034 - Acceptance Criteria

Excerpt Include
SWEHBVD:SWE-034 - Acceptance Criteria
SWEHBVD:SWE-034 - Acceptance Criteria
nopaneltrue

Include Page
SWE-034 - SA Task1
SWE-034 - SA Task1

SWE-036 - Software Process Determination

Excerpt Include
SWEHBVD:SWE-036 - Software Process Determination
SWEHBVD:SWE-036 - Software Process Determination
nopaneltrue

Include Page
SWE-036 - SA Task1
SWE-036 - SA Task1

Include Page
SWE-036 - SA Task2
SWE-036 - SA Task2

SWE-037 - Software Milestones

Excerpt Include
SWEHBVD:SWE-037 - Software Milestones
SWEHBVD:SWE-037 - Software Milestones
nopaneltrue

Include Page
SWE-037 - SA Task1
SWE-037 - SA Task1

Include Page
SWE-037 - SA Task2
SWE-037 - SA Task2

SWE-039 - Software Supplier Insight

Excerpt Include
SWEHBVD:SWE-039 - Software Supplier Insight
SWEHBVD:SWE-039 - Software Supplier Insight
nopaneltrue

Include Page
SWE-039 - SA Task1
SWE-039 - SA Task1

Include Page
SWE-039 - SA Task2
SWE-039 - SA Task2

Include Page
SWE-039 - SA Task3
SWE-039 - SA Task3

Include Page
SWE-039 - SA Task4
SWE-039 - SA Task4

Include Page
SWE-039 - SA Task5
SWE-039 - SA Task5

Include Page
SWE-039 - SA Task6
SWE-039 - SA Task6

Include Page
SWE-039 - SA Task7
SWE-039 - SA Task7

Include Page
SWE-039 - SA Task8
SWE-039 - SA Task8

SWE-040 - Access to Software Products

Excerpt Include
SWEHBVD:SWE-040 - Access to Software Products
SWEHBVD:SWE-040 - Access to Software Products
nopaneltrue

Include Page
SWE-040 - SA Task1
SWE-040 - SA Task1

SWE-042 - Source Code Electronic Access

Excerpt Include
SWEHBVD:SWE-042 - Source Code Electronic Access
SWEHBVD:SWE-042 - Source Code Electronic Access
nopaneltrue

Include Page
SWE-042 - SA Task1
SWE-042 - SA Task1

SWE-139 - Shall Statements

Excerpt Include
SWEHBVD:SWE-139 - Shall Statements
SWEHBVD:SWE-139 - Shall Statements
nopaneltrue

Include Page
SWE-139 - SA Task1
SWE-139 - SA Task1

SWE-121 - Document Tailored Requirements

Excerpt Include
SWEHBVD:SWE-121 - Document Tailored Requirements
SWEHBVD:SWE-121 - Document Tailored Requirements
nopaneltrue

Include Page
SWE-121 - SA Task1
SWE-121 - SA Task1

Include Page
SWE-121 - SA Task2
SWE-121 - SA Task2

SWE-125 - Requirements Compliance Matrix

Excerpt Include
SWEHBVD:SWE-125 - Requirements Compliance Matrix
SWEHBVD:SWE-125 - Requirements Compliance Matrix
nopaneltrue

Include Page
SWE-125 - SA Task1
SWE-125 - SA Task1

Include Page
SWE-125 - SA Task2
SWE-125 - SA Task2

SWE-027 - Use of Commercial, Government, and Legacy Software

excerpt-include

SWEHBVD:SWE-027 - Use of Commercial, Government, and Legacy Software
SWEHBVD:SWE-027 - Use of Commercial, Government, and Legacy Software
nopaneltrue

Include Page
SWE-027 - SA Task1
SWE-027 - SA Task1

SWE-151 - Cost Estimate Conditions

Excerpt Include
SWEHBVD:SWE-151 - Cost Estimate Conditions
SWEHBVD:SWE-151 - Cost Estimate Conditions
nopaneltrue

Include Page
SWE-151 - SA Task1
SWE-151 - SA Task1

SWE-016 - Software Schedule

Excerpt Include
SWEHBVD:SWE-016 - Software Schedule
SWEHBVD:SWE-016 - Software Schedule
nopaneltrue

Include Page
SWE-016 - SA Task2
SWE-016 - SA Task2

SWE-046 - Supplier Software Schedule

Excerpt Include
SWEHBVD:SWE-046 - Supplier Software Schedule
SWEHBVD:SWE-046 - Supplier Software Schedule
nopaneltrue

Include Page
SWE-046 - SA Task1
SWE-046 - SA Task1

SWE-020 - Software Classification

Excerpt Include
SWEHBVD:SWE-020 - Software Classification
SWEHBVD:SWE-020 - Software Classification
nopaneltrue

Include Page
SWE-020 - SA Task1
SWE-020

SITE:SWE-034 - SA Task1

- SA Task1

2.2 Topics and other Supporting Materials

Note

This section is for SWEHB pages, other than SWEs, that directly support the activity. This section contains Topics, document content pages, PATs, and other pages. 

  • Software Assurance Plan
    • Excerpt Include
      SWEHBVD:8.51 - Software Assurance Plan
      SWEHBVD:8.51 - Software Assurance Plan
      nopaneltrue
  • Link to the Topic or page goes hereExcerpt include for the Topic or page goes here (Remove Surrounding Panel)

2.3 Other Associated SWEs, Topics, etc.

Note

Includes other SWEHB pages that are indirectly associated with the activity. May include SWEs, Topics, document definition pages, PATs, etc. They may have been mentioned in the guidance of another page. 

  • Include page for the PAT page goes here