A

3.1.2.2 The project shall identify, initiate corrective actions, and track until closure inconsistencies among requirements, project plans, and software products.

Difference between A and B

No change

B

4.1.3.2 The project manager shall identify, initiate corrective actions, and track until closure inconsistencies among requirements, project plans, and software products.

Difference between B and C

No change

C

4.1.6 The project manager shall identify, initiate corrective actions, and track until closure inconsistencies among requirements, project plans, and software products. 