SWE-046 - Last used in rev NPR 7150.2D

RevSWE Statement
A

2.6.2.4 The project shall require the software supplier(s) to provide a software schedule for the project's review and schedule updates as requested.

Difference between A and B

No change

B

3.13.3 The project manager  shall require the software supplier(s) to provide a software schedule for the project's review and schedule updates as requested.

Difference between B and C

Changed "software supplier(s)" TO "software developer(s)"

C

3.3.3 The project manager shall require the software developer(s) to provide a software schedule for the project's review, and schedule updates as requested.

Difference between C and DNo change
D

3.3.3 The project manager shall require the software developer(s) to provide a software schedule for the project’s review, and schedule updates as requested.